Data center project · Sedgwick County, Kansas
Monarch Energy land assembly, Colwich-Andale area
Inquiry only · Purchase agreements for more than 300 acres of farmland over the Equus Beds aquifer by a San Diego developer that KMUW said recently closed a $12 billion data center deal in Rockford, Illinois.
- Status
- Inquiry only · as of March 16, 2026
- Location
- Between 183rd and 215th streets West off 53rd Street North, near Colwich and Andale · Sedgwick County
- Status note
- Purchase agreements only; no zoning application, and the county's interim development control bars data center applications through Dec. 24, 2026.
- Power
- Not reported
No power figure; the company has not described a project. - Land
- 300 acres
- Developer and team
- Monarch Energy
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- March 16, 2026 KMUW found county records showing Monarch's CEO signed 2025 purchase agreements with two owners covering more than 300 acres. (KMUW, March 16, 2026)
Conflicts and open questions
- Sellers were asked to sign nondisclosure agreements, per KMUW.
- Acreage is 'more than 300'.
Have records about this project? Send them to tips@signaldata.org.