Data center project · Miami County, Kansas
Project Catalyst (Alcove Development), Osawatomie
Proposed · A predevelopment deal between Osawatomie and a Lawrence housing developer for a data center campus on city land, announced as the largest project in Miami County history. Also known as: Project Catalyst, Northland Data Centers.
- Status
- Proposed · as of July 23, 2026
- Location
- Northern edge of Osawatomie, across from Osawatomie State Hospital · Miami County
- Status note
- The city signed a three-year predevelopment agreement; the mayor said in June 2026 that no applications or permits had been filed.
- Power
- 500 MW
'500+ MW' in the city's May 2026 announcement; February 2026 records reported by KCTV called for 50 to 150 MW on about 115 acres. - Land
- 283 acres
- Investment
- $900 million to $1.1 billion in February 2026 terms (KCTV); KSHB described preliminary renderings of a $1 billion project; no figure found for the expanded plan
- Developer and team
- Alcove Development
- Utility
- Evergy (franchise agreement negotiated in 2026)
- Water
- February 2026 terms called for the city to supply 1 million gallons a day; the May announcement described an air-cooled design.
- Incentives
- February 2026 terms reported by KCTV: city land sale at $10,000 an acre and a 50% property tax cut for 10 years; not final.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- July 23, 2026 The council packet listed an Evergy franchise ordinance tied to the potential data center parcels (no action) and included minutes of the July 9 meeting, where residents questioned the project in public comment. (City of Osawatomie, July 23, 2026)
- June 4, 2026 The mayor said the agreement only grants due diligence and that no applications, permits or council votes had occurred. (KSHB 41, June 4, 2026)
- May 29, 2026 The city and Alcove announced a 500+ MW campus on a 283-acre site with projected annual local revenues at full build-out. (KCTV5, May 29, 2026)
- Feb. 18, 2026 KCTV reported a proposed deal to sell about 115 city acres for a $0.9 billion to $1.1 billion data center needing 50 to 150 MW; records named the buyer Northland Data Centers. (KCTV5, Feb. 18, 2026)
Conflicts and open questions
- Size and power differ sharply between the February records (115 acres, 50-150 MW) and the May announcement (283 acres, 500+ MW).
- How 'Northland Data Centers' relates to Alcove was not confirmed in the sources reviewed.
- A Miami County moratorium on unincorporated land was reported but not verified; it would not reach this in-city site.
Have records about this project? Send them to tips@signaldata.org.