Data centers · Wyandotte County, Kansas

Wyandotte County

3 projects on record

← Statewide map
Allen CountyAnderson CountyAtchison CountyBarber CountyBarton CountyBourbon CountyBrown CountyButler CountyChase CountyChautauqua CountyCherokee CountyCheyenne CountyClark CountyClay CountyCloud CountyCoffey CountyComanche CountyCowley CountyCrawford CountyDecatur CountyDickinson CountyDoniphan CountyDouglas CountyEdwards CountyElk CountyEllis CountyEllsworth CountyFinney CountyFord CountyFranklin CountyGeary CountyGove CountyGraham CountyGrant CountyGray CountyGreeley CountyGreenwood CountyHamilton CountyHarper CountyHarvey CountyHaskell CountyHodgeman CountyJackson CountyJefferson CountyJewell CountyJohnson CountyKearny CountyKingman CountyKiowa CountyLabette CountyLane CountyLeavenworth CountyLincoln CountyLinn CountyLogan CountyLyon CountyMarion CountyMarshall CountyMcPherson CountyMeade CountyMiami CountyMitchell CountyMontgomery CountyMorris CountyMorton CountyNemaha CountyNeosho CountyNess CountyNorton CountyOsage CountyOsborne CountyOttawa CountyPawnee CountyPhillips CountyPottawatomie CountyPratt CountyRawlins CountyReno CountyRepublic CountyRice CountyRiley CountyRooks CountyRush CountyRussell CountySaline CountyScott CountySedgwick CountySeward CountyShawnee CountySheridan CountySherman CountySmith CountyStafford CountyStanton CountyStevens CountySumner CountyThomas CountyTrego CountyWabaunsee CountyWallace CountyWashington CountyWichita CountyWilson CountyWoodson CountyWyandotte CountyProject Red Wolf (Red Wolf DCD Properties), Parallel Parkway · Approved · 600 MWProject Linda (Wyandotte County) · Inquiry only · 200 MWProject Yardbird (former Quindaro Power Station) · Proposed · 192 MW
Projects in Wyandotte County
Project Red Wolf (Red Wolf DCD Properties), Parallel ParkwayRed Wolf DCD Properties600ApprovedJan. 202650 MW+
Project Linda (Wyandotte County)Not disclosed200Inquiry onlyJan. 202650 MW+
Project Yardbird (former Quindaro Power Station)PowerTransitions192ProposedJan. 202650 MW+

Updates, newest first

  1. Jan. 28, 2026 Project Red Wolf (Red Wolf DCD Properties), Parallel Parkway · The Beacon reported the project still had no final agreement with BPU or the Unified Government and that the lawsuit remained pending. (KCUR (The Beacon), Jan. 29, 2026)
  2. Jan. 28, 2026 Project Yardbird (former Quindaro Power Station) · The Beacon reported the developer was still completing environmental assessments under its option and had no final agreement. (KCUR (The Beacon), Jan. 29, 2026)
  3. Jan. 28, 2026 Project Linda (Wyandotte County) · BPU officials told The Beacon the project was preparing a Southwest Power Pool study request, a required step before it can proceed. (KCUR (The Beacon), Jan. 29, 2026)
  4. Oct. 29, 2025 Project Red Wolf (Red Wolf DCD Properties), Parallel Parkway · A district judge in Wyandotte County refused the Unified Government's request to dismiss residents' claims over the south tract and said north-tract claims could proceed once commissioners make a final decision. (High Plains Public Radio (Kansas Reflector), Nov. 10, 2025)
  5. July 31, 2025 Project Red Wolf (Red Wolf DCD Properties), Parallel Parkway · After protest petitions, the north-side rezoning failed to reach the required supermajority on a 7-3 vote; the south side no longer needed one after eight petition signers withdrew. (High Plains Public Radio (Kansas Reflector), Nov. 10, 2025)
  6. June 2025 Project Yardbird (former Quindaro Power Station) · The Unified Government said it was weighing a $13.6 million sale of the 85-acre plant site to Houston-based PowerTransitions for a data center needing 192 MW. (Flatland KC, July 7, 2025)
  7. May 28, 2025 Project Red Wolf (Red Wolf DCD Properties), Parallel Parkway · On a 4-2 vote, planning commissioners recommended the rezoning, plat and master plan changes; the Journal-World reported the developer would pay for two BPU substations to handle 600 MW, more than BPU's roughly 500 MW system. (Lawrence Journal-World, May 29, 2025)
  8. May 27, 2025 Project Red Wolf (Red Wolf DCD Properties), Parallel Parkway · The New York-based developer asked the Unified Government planning commission to rezone land northwest of the Kansas Speedway for six buildings. (KSAL, May 27, 2025)

Statewide

SB 98 (signed April 24, 2025; in effect July 1, 2025) offers a qualified firm a sales tax exemption lasting 20 years from the start of operations on the costs of building, equipping and servicing a qualified data center (electricity is not an eligible cost). To qualify, the firm must commit to at least $250 million in eligible investment by its fifth year of operations, start construction within 10 years of its agreement with the Secretary of Commerce, create and keep 20 new jobs within two calendar years, adopt water conservation and reuse practices and buy power for 10 years from the utility certified for the site; after an uncured breach (120 days' notice), Commerce may recover or end the exemption. The enrolled text reviewed sets no application deadline or sunset for the exemption itself. (Kansas Legislature, April 24, 2025; Kansas Legislative Research Department, 2025; Kansas Legislature, April 11, 2025) SB 98 also requires the Secretary of Commerce to get approval from the state's fusion center oversight board before giving any public financial help to a qualified data center, after the Kansas Intelligence Fusion Center reviews its equipment and software for threats to critical infrastructure; the board may approve, require changes or deny. The same bill amended K.S.A. 66-101j so a qualified data center cannot receive an electric utility's economic development rate discount. (Kansas Legislature, April 11, 2025; Kansas Legislative Research Department, 2025) KCC docket 25-EKME-315-TAR: Evergy filed its Large Load Power Service (LLPS) tariff for its Kansas Central and Kansas Metro territories on Feb. 11, 2025; all active parties (including the Data Center Coalition, Google, the Sierra Club and NRDC, per trade press) filed a unanimous settlement on Aug. 18, 2025, and the commission approved it on Nov. 6, 2025. The plan covers new or expanding loads of 75 MW or more (CURB's wording; the KCC's briefing and Utility Dive say above 75 MW), sets a 12-year minimum term after up to five years of ramp, bills at least 80% of contract demand, requires collateral of up to two years of minimum bills and puts loads of 25 MW or more through a queue that moves up to four projects at a time; it applies only to Evergy, not to cooperatives or municipal utilities such as KCK's Board of Public Utilities. (Kansas Corporation Commission, Jan. 15, 2026; Citizens' Utility Ratepayer Board, 2025; Utility Dive, Nov. 10, 2025) Estimates of how much more LLPS customers will pay than existing large industrial customers differ by source: 7% to 10% (KCC staff, as cited from the order by Utility Dive) or 8% to 10% on an all-in bill basis and 16% to 19% on base demand and energy charges (the KCC's January 2026 legislative briefing); these are projected rate differences, not bills paid. Evergy's February 2025 filing reported more than 20 prospective large-load customers totaling over 6 GW in Kansas, per Utility Dive. (Kansas Corporation Commission, Jan. 15, 2026; Utility Dive, Nov. 10, 2025) 2026 session: SB 531, requested by Sen. Murphy, would have barred new large-load data centers in any county with a drought emergency declared in the prior three years; it died in committee. KMUW reported that Senate Majority Leader Chase Blasi had earlier urged, then unsuccessfully sought to legislate, a three-year pause in drought counties. Other 2026 data center bills listed by trackers (SB 400 on closed-loop cooling, SB 526 on zoning eligibility for the SB 98 exemption) were not opened in the Legislature's records for this review. (Kansas Legislature, April 10, 2026; KMUW, May 7, 2026) Citizen-initiated ordinances under K.S.A. 12-3013 were tried in several cities in 2026: petitions to ban large or 'high impact' data centers were certified or verified in Edgerton and Ottawa and filed in El Dorado and Emporia. Edgerton, El Dorado and Emporia asked district courts whether the measures are a proper subject for initiative, and Ottawa residents sued their city. Judges ordered the Emporia and Ottawa questions onto the November 2026 ballot while validity is decided, and ruled for the El Dorado petitioners, leaving that city to adopt the ordinance or put it to voters; Edgerton's case was pending. (City of Edgerton, July 24, 2026; KWCH 12, Aug. 25, 2026; WIBW, Aug. 20, 2026; KSHB 41, Sept. 3, 2026) Kansas data centers →