Data center project · Wyandotte County, Kansas
Project Red Wolf (Red Wolf DCD Properties), Parallel Parkway
Approved · A six-building, 1.8 million-square-foot hyperscale campus proposed on farmland in western Wyandotte County, the largest of three code-named projects BPU was weighing in early 2026. Also known as: Project Red Wolf.
- Status
- Approved · as of Jan. 2026
- Location
- Western Kansas City, Kansas, northwest of the Kansas Speedway, on both sides of Parallel Parkway · Wyandotte County
- Status note
- Zoning for the south tract was approved in 2025; the north tract failed a supermajority vote after a protest petition, and a residents' lawsuit over the zoning process was pending in January 2026.
- Power
- 600 MW
The Beacon (KCUR) reported the project at 600 MW, split about 300 MW north and 300 MW south of Parallel Parkway; the Journal-World reported in 2025 that the two BPU substations the developer pledged to fund would handle 600 MW. A planned load, not a measured one. - Floor area
- 1,800,000 sq ft
- Land
- 548 acres
- Investment
- $12.6 billion as reported in May 2025 (later reported as about $12 billion)
- Developer and team
- Red Wolf DCD Properties
- End user
- Not disclosed
- Utility
- Kansas City Board of Public Utilities (BPU), with power drawn from the Southwest Power Pool
- Incentives
- No project-specific incentive found; the developer pledged to pay for utility upgrades including two BPU substations.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Jan. 28, 2026 The Beacon reported the project still had no final agreement with BPU or the Unified Government and that the lawsuit remained pending. (KCUR (The Beacon), Jan. 29, 2026)
- Oct. 29, 2025 A district judge in Wyandotte County refused the Unified Government's request to dismiss residents' claims over the south tract and said north-tract claims could proceed once commissioners make a final decision. (High Plains Public Radio (Kansas Reflector), Nov. 10, 2025)
- July 31, 2025 After protest petitions, the north-side rezoning failed to reach the required supermajority on a 7-3 vote; the south side no longer needed one after eight petition signers withdrew. (High Plains Public Radio (Kansas Reflector), Nov. 10, 2025)
- May 28, 2025 On a 4-2 vote, planning commissioners recommended the rezoning, plat and master plan changes; the Journal-World reported the developer would pay for two BPU substations to handle 600 MW, more than BPU's roughly 500 MW system. (Lawrence Journal-World, May 29, 2025)
- May 27, 2025 The New York-based developer asked the Unified Government planning commission to rezone land northwest of the Kansas Speedway for six buildings. (KSAL, May 27, 2025)
Conflicts and open questions
- KSAL's May 2025 preview said the request was to rezone 24 acres; later reporting describes a site of about 548 to 550 acres.
- The lawsuit's allegations about the petition and recusal process are claims by the plaintiffs, not findings.
- No 2026 court ruling or Unified Government vote was found in the sources reviewed.
Have records about this project? Send them to tips@signaldata.org.