Data center project · Carroll County, Kentucky
Carrollton Industrial Campus
Proposed · A $9.6 billion hyperscale campus planned on about 550 acres, including city land once meant for a wastewater plant expansion.
- Status
- Proposed · as of Sept. 23, 2026
- Location
- Greens Bottom Road, east of I-71, outside Carrollton · Carroll County
- Power
- 800 MW
An estimated 800 MW data center, as reported by Spectrum News 1; not a utility contract figure. - Land
- 550 acres
- Investment
- $9.6 billion
- Developer and team
- Poe Companies; PowerHouse Data Centers
- Incentives
- Poe projects $96.4 million a year in local taxes over the first 20 years, including about $11.5 million to Carrollton under a payment in lieu of taxes agreement (developer projection).
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Sept. 23, 2026 Poe released its tax revenue projections; nearby residents said they had little notice. (Spectrum News 1, Sept. 23, 2026)
- Sept. 2026 Residents filed local ethics complaints arguing that some Carrollton council members should have abstained from votes on land deals with a data center developer. (Kentucky Lantern, Oct. 12, 2026)
- July 27, 2026 The city confirmed the land sale and said the developers will pay for transmission upgrades. (Data Center Dynamics, July 27, 2026)
- July 25, 2026 Poe and PowerHouse said they hold purchase options on 550 acres and have done power and system impact studies. (Local 12 (WKRC), from the Cincinnati Business Courier, July 25, 2026)
Conflicts and open questions
- The ethics complaints are allegations; no finding was reported.