Data center project · Oldham County, Kentucky
Project Lincoln, Oldham County
Withdrawn · A $6 billion, eight-building campus on 267 acres of farmland that moved to a smaller industrial site after local opposition and was then dropped. Also known as: Project Lincoln.
- Status
- Withdrawn · as of July 3, 2025
- Location
- Farmland on North Highway 53 near La Grange (later Commerce Parkway, Sauerbeck Drive-In site) · Oldham County
- Status note
- Western Hospitality Partners withdrew both its Highway 53 application and a smaller replacement plan.
- Power
- 600 MW
Up to 600 MW for the original Highway 53 plan as reported by DCD; no figure for the smaller replacement plan. - Floor area
- 2,500,000 sq ft
- Land
- 267 acres
- Investment
- $6 billion (original); about $1.5 billion (replacement)
- Developer and team
- Western Hospitality Partners
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- July 3, 2025 WHP said it was pulling the Commerce Parkway application and the project would not go forward. (WAVE, July 3, 2025)
- July 1, 2025 The Fiscal Court adopted a 150-day moratorium on data center applications, through Nov. 28, with no exemption for projects already filed. (Data Center Dynamics, July 14, 2025)
- June 10, 2025 After opposition, the developer withdrew the Highway 53 application and filed for two buildings totaling 312,000 sq ft (about $1.5 billion) on the drive-in property next to the Dynegy plant. (Data Center Dynamics, June 10, 2025)