Data center project · Jefferson County, Kentucky
PowerHouse Louisville, Camp Ground Road
Under construction · Kentucky's first hyperscale campus: a plan of seven buildings (server warehouses, an office and a guardhouse) on heavy-industrial land in west Louisville, approved by the Planning Commission without a rezoning. Also known as: Camp Ground Road data center.
- Status
- Under construction · as of Aug. 4, 2026
- Location
- Camp Ground Road near Shively, west Louisville · Jefferson County
- Status note
- LPM described the campus as under construction in August 2026; the first 130 MW phase targets late 2026.
- Power
- 402 MW
Power capacity LG&E has secured: 335 MW initially, expanding to 402 MW (EPIC report). The developers have said about 400 MW. Not IT load. - Floor area
- 1,800,000 sq ft
Up to 1.8 million sq ft (DCD, January 2025); no square-foot total was found for the 2026 revised plans. - Land
- 154 acres
- Investment
- About $11 billion over the project's life (EPIC report)
- Developer and team
- Poe Companies; PowerHouse Data Centers
- Utility
- LG&E (new switch station and on-site substation)
- Water
- Louisville Water told the developers it can meet demand, according to their attorney.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Aug. 4, 2026 LPM reported that the campus was under construction and that Louisville's pending moratorium would not affect it. (Louisville Public Media, Aug. 4, 2026)
- June 2026 EPIC put lifetime investment at about $11 billion and said the first 130 MW phase targets commercial operation in late 2026. (Kentucky Energy Planning and Inventory Commission, June 2026)
- March 5, 2026 The Louisville Planning Commission approved revised plans for seven buildings, voting six in favor after more than 20 residents spoke against it; because the land is zoned heavy industrial, no Metro Council vote was needed. (Louisville Public Media, March 5, 2026)
- Jan. 17, 2025 PowerHouse and Poe announced a campus of about 154 acres on Camp Ground Road near the Cane Run plant, with 335 MW of secured power rising to 402 MW and a first 130 MW phase due in October 2026. (Data Center Dynamics, Jan. 17, 2025)
Conflicts and open questions
- Plans first approved in summer 2025 were revised in 2026 to add properties and make the server warehouses two stories (LPM). Acreage is 154 in the January 2025 announcement; Spectrum News 1 described a 150-acre campus in July 2026.
Have records about this project? Send them to tips@signaldata.org.