Data center project · Greenup County, Kentucky
Rubix data center, former AK Steel site
Proposed · A 2 GW, eight-building campus proposed for the former steel mill brownfield on the Ohio River.
- Status
- Proposed · as of July 22, 2026
- Location
- Former AK Steel Ashland Works site, Russell · Greenup County
- Status note
- Russell passed a moratorium on data center applications in June 2026; the developer's consultant told the mayor it could impede the project.
- Power
- 2,000 MW
2 GW, stated by the company in its answers to the city of Russell. - Land
- 425 acres
A 425-acre brownfield, per the Russell mayor's July 10 letter (Kentucky Lantern). - Investment
- $8 billion to $12 billion in computing infrastructure (company)
- Developer and team
- Rubix Data Centers (Submer Group)
- Water
- About 55 million gallons a year (company)
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- July 22, 2026 The Lantern reported the company's written answers to the city of Russell, posted on the city website: eight two-story buildings, 2 GW, $8 billion to $12 billion, and about 200 permanent jobs averaging $125,000. (Kentucky Lantern (via Route Fifty), July 22, 2026)