Data center project · Greenup County, Kentucky

Rubix data center, former AK Steel site

Proposed · A 2 GW, eight-building campus proposed for the former steel mill brownfield on the Ohio River.

← Kentucky data centers
Adair CountyAllen CountyAnderson CountyBallard CountyBarren CountyBath CountyBell CountyBoone CountyBourbon CountyBoyd CountyBoyle CountyBracken CountyBreathitt CountyBreckinridge CountyBullitt CountyButler CountyCaldwell CountyCalloway CountyCampbell CountyCarlisle CountyCarroll CountyCarter CountyCasey CountyChristian CountyClark CountyClay CountyClinton CountyCrittenden CountyCumberland CountyDaviess CountyEdmonson CountyElliott CountyEstill CountyFayette CountyFleming CountyFloyd CountyFranklin CountyFulton CountyGallatin CountyGarrard CountyGrant CountyGraves CountyGrayson CountyGreen CountyGreenup CountyHancock CountyHardin CountyHarlan CountyHarrison CountyHart CountyHenderson CountyHenry CountyHickman CountyHopkins CountyJackson CountyJefferson CountyJessamine CountyJohnson CountyKenton CountyKnott CountyKnox CountyLarue CountyLaurel CountyLawrence CountyLee CountyLeslie CountyLetcher CountyLewis CountyLincoln CountyLivingston CountyLogan CountyLyon CountyMadison CountyMagoffin CountyMarion CountyMarshall CountyMartin CountyMason CountyMcCracken CountyMcCreary CountyMcLean CountyMeade CountyMenifee CountyMercer CountyMetcalfe CountyMonroe CountyMontgomery CountyMorgan CountyMuhlenberg CountyNelson CountyNicholas CountyOhio CountyOldham CountyOwen CountyOwsley CountyPendleton CountyPerry CountyPike CountyPowell CountyPulaski CountyRobertson CountyRockcastle CountyRowan CountyRussell CountyScott CountyShelby CountySimpson CountySpencer CountyTaylor CountyTodd CountyTrigg CountyTrimble CountyUnion CountyWarren CountyWashington CountyWayne CountyWebster CountyWhitley CountyWolfe CountyWoodford CountyRubix data center, former AK Steel site · Proposed · 2,000 MW
Status
Proposed · as of July 22, 2026
Location
Former AK Steel Ashland Works site, Russell · Greenup County
Status note
Russell passed a moratorium on data center applications in June 2026; the developer's consultant told the mayor it could impede the project.
Power
2,000 MW
2 GW, stated by the company in its answers to the city of Russell.
Land
425 acres
A 425-acre brownfield, per the Russell mayor's July 10 letter (Kentucky Lantern).
Investment
$8 billion to $12 billion in computing infrastructure (company)
Developer and team
Rubix Data Centers (Submer Group)
Water
About 55 million gallons a year (company)
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. July 22, 2026 The Lantern reported the company's written answers to the city of Russell, posted on the city website: eight two-story buildings, 2 GW, $8 billion to $12 billion, and about 200 permanent jobs averaging $125,000. (Kentucky Lantern (via Route Fifty), July 22, 2026)