Data center project · Aroostook County, Maine

Loring LiquidCool Data Center

Proposed · An AI data center using immersion cooling in a leased warehouse at the former Loring Air Force Base, small now but planned to grow to 26 MW. Also known as: LiquidCool Loring.

← Maine data centers
Androscoggin CountyAroostook CountyCumberland CountyFranklin CountyHancock CountyKennebec CountyKnox CountyLincoln CountyOxford CountyPenobscot CountyPiscataquis CountySagadahoc CountySomerset CountyWaldo CountyWashington CountyYork CountyLoring LiquidCool Data Center · Proposed · 26 MW
Status
Proposed · as of Feb. 23, 2026
Location
Building 7230, Green 4 Maine campus, Loring Commerce Centre, Limestone · Aroostook County
Status note
Leased space in an existing warehouse; opening was expected about six months after the October 2025 announcement, and no opening was confirmed in the sources reviewed.
Power
26 MW
Under 50 MW: the company said it would open at 2 MW already in the building and could reach 26 MW under a Versant will-serve agreement; the landlord earlier described a 5-6 MW first phase.
Floor area
115,000 sq ft
Developer and team
Loring LiquidCool Data Center LLC (LiquidCool Solutions technology); Green 4 Maine (landlord)
Utility
Versant Power
Water
Immersion liquid cooling; the company says it uses no water to cool servers.
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Feb. 23, 2026 LiquidCool's vice chair said the center would open at 2 MW and could reach 26 MW, and would cap demand at 20 MW if LD 307 passed without a waiver. (The Maine Monitor (from the Daily Yonder), Feb. 23, 2026)
  2. Oct. 14, 2025 Green 4 Maine announced a long-term lease of 115,000 square feet to Loring LiquidCool Data Center, starting at 5-6 MW, with talk of more data centers on the campus. (Bangor Daily News, Oct. 14, 2025; Mainebiz, Oct. 17, 2025)

Conflicts and open questions

  • Initial size differs by source: 5-6 MW (landlord, October 2025) and 2 MW (company, February 2026).

Have records about this project? Send them to tips@signaldata.org.