Data center project · Monroe County, Michigan

Project Cherry Blossom

Withdrawn · A proposed data center on a township-owned former golf course that ended when the developer's exclusive letter of intent lapsed and the township adopted a moratorium. Also known as: Cherry Blossom Devco.

← Michigan data centers
Alcona CountyAlger CountyAllegan CountyAlpena CountyAntrim CountyArenac CountyBaraga CountyBarry CountyBay CountyBenzie CountyBerrien CountyBranch CountyCalhoun CountyCass CountyCharlevoix CountyCheboygan CountyChippewa CountyClare CountyClinton CountyCrawford CountyDelta CountyDickinson CountyEaton CountyEmmet CountyGenesee CountyGladwin CountyGogebic CountyGrand Traverse CountyGratiot CountyHillsdale CountyHoughton CountyHuron CountyIngham CountyIonia CountyIosco CountyIron CountyIsabella CountyJackson CountyKalamazoo CountyKalkaska CountyKent CountyKeweenaw CountyLake CountyLapeer CountyLeelanau CountyLenawee CountyLivingston CountyLuce CountyMackinac CountyMacomb CountyManistee CountyMarquette CountyMason CountyMecosta CountyMenominee CountyMidland CountyMissaukee CountyMonroe CountyMontcalm CountyMontmorency CountyMuskegon CountyNewaygo CountyOakland CountyOceana CountyOgemaw CountyOntonagon CountyOsceola CountyOscoda CountyOtsego CountyOttawa CountyPresque Isle CountyRoscommon CountySaginaw CountySanilac CountySchoolcraft CountyShiawassee CountySt. Clair CountySt. Joseph CountyTuscola CountyVan Buren CountyWashtenaw CountyWayne CountyWexford CountyProject Cherry Blossom · Withdrawn
Status
Withdrawn · as of June 9, 2026
Location
1500 North Dixie Highway (former River Raisin Golf Course), Frenchtown Charter Township · Monroe County
Status note
Exclusive letter of intent expired in May 2026; the township board said it is not pursuing a data center on its property.
Power
Not reported
Power not stated in sources reviewed.
Developer and team
Cloverleaf Infrastructure (through Cherry Blossom Devco)
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. June 9, 2026 Board stated it no longer wants a data center on the site; no agreement with a data center developer was still in effect. (Frenchtown Charter Township Board, June 2026)
  2. April 28, 2026 Board adopted a moratorium on data center and other high-resource-demand applications. (Frenchtown Charter Township Board, June 2026)
  3. Jan. 9, 2026 Township board signed a 60-day letter of intent giving Cherry Blossom Devco exclusive data center talks on the property; the developer extended it in March. (Frenchtown Charter Township Board, June 2026)

Conflicts and open questions

  • The Gander reports about 200 acres; acreage not stated in the township statement.

Have records about this project? Send them to tips@signaldata.org.