Data center project · Wayne County, Michigan
Project Cannoli (Google)
Approved · Google's six-building, 1-gigawatt campus on industrial land near the Detroit airport, with utility contracts approved by state regulators and final local site plan approval in October 2026. Also known as: Project Cannoli.
- Status
- Approved · as of Oct. 14, 2026
- Location
- Haggerty Road and I-94, west of Detroit Metropolitan Airport, Van Buren Township · Wayne County
- Status note
- Planning Commission approved the final site plan 5-1; residents reported early site work under way since August 2026.
- Power
- 1,000 MW
1 GW site; the separate 2.7 GW figure is Google's resource commitment with DTE, not site load (township FAQ). - Land
- 282 acres
- Investment
- Not stated in sources reviewed
- Developer and team
- Panattoni Development Co.
- End user
- Utility
- DTE Electric; 20-year primary supply agreement and clean capacity agreement approved by the MPSC (Case No. U-22058) after a contested case; Google pays for up to 1,600 MW of renewables and 480 MW of storage; service expected from December 2027
- Water
- Up to 3.6 million gallons a day from the Great Lakes Water Authority (reported); 13.55 acres of wetlands to be filled under an EGLE permit approved in August 2026
- Incentives
- Half-price local taxes for 12 years approved by the township and Wayne County, estimated at $125 million; the Wayne County Commission overrode County Executive Warren Evans' veto on Oct. 1, 2026. Google to pay the township $15.4 million for local infrastructure and guarantee at least 51 jobs (reported).
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Oct. 14, 2026 Van Buren Township Planning Commission approved the final site plan 5-1. (Bridge Michigan, Oct. 15, 2026)
- Oct. 1, 2026 MPSC approved the DTE-Google contracts with a 20-year term, 80% minimum billing and a termination payment of at least 15 years of minimum charges; the same day the Wayne County Commission overrode a veto of the tax break. (Michigan Public Service Commission, Oct. 1, 2026; Michigan Public (from Planet Detroit), Oct. 2, 2026)
- June 16, 2026 EGLE held a hearing on the wetland permit; the plan would fill 13.55 acres of wetlands, offset with mitigation credits. (Planet Detroit, June 17, 2026)
- March 17, 2026 Google identified itself as the end user and DTE announced a 20-year power deal, which DTE said it would file with the MPSC that day. (Bridge Michigan, March 17, 2026)
- Feb. 11, 2026 Panattoni presented the project to the township Planning Commission; township FAQ and meeting materials are posted on the township's project page. (Van Buren Charter Township, undated)
Conflicts and open questions
- The site is already zoned industrial, so no rezoning was needed (township FAQ and reporting).
- Water use estimates range from 2 million to 3.6 million gallons a day across sources.
Have records about this project? Send them to tips@signaldata.org.