Data center campus · Becker, former Xcel Energy Sherco land, Sherburne County, Minnesota

Amazon Becker Data Center

Stalled as of May 23, 2025

Amazon bought 348 acres of former Xcel land near Sherco in Becker in 2024 for a data center, then put development on hold in May 2025. Also known as: Elk River Technologies site.

Cite← Minnesota data centers
Aitkin CountyAnoka CountyBecker CountyBeltrami CountyBenton CountyBig Stone CountyBlue Earth CountyBrown CountyCarlton CountyCarver CountyCass CountyChippewa CountyChisago CountyClay CountyClearwater CountyCook CountyCottonwood CountyCrow Wing CountyDakota CountyDodge CountyDouglas CountyFaribault CountyFillmore CountyFreeborn CountyGoodhue CountyGrant CountyHennepin CountyHouston CountyHubbard CountyIsanti CountyItasca CountyJackson CountyKanabec CountyKandiyohi CountyKittson CountyKoochiching CountyLac qui Parle CountyLake CountyLake of the Woods CountyLe Sueur CountyLincoln CountyLyon CountyMahnomen CountyMarshall CountyMartin CountyMcLeod CountyMeeker CountyMille Lacs CountyMorrison CountyMower CountyMurray CountyNicollet CountyNobles CountyNorman CountyOlmsted CountyOtter Tail CountyPennington CountyPine CountyPipestone CountyPolk CountyPope CountyRamsey CountyRed Lake CountyRedwood CountyRenville CountyRice CountyRock CountyRoseau CountyScott CountySherburne CountySibley CountySt. Louis CountyStearns CountySteele CountyStevens CountySwift CountyTodd CountyTraverse CountyWabasha CountyWadena CountyWaseca CountyWashington CountyWatonwan CountyWilkin CountyWinona CountyWright CountyYellow Medicine CountyAmazon Becker Data Center · Stalled
PowerNot statedNot reported in the records found
Site348acres

Who is behind it

ProjectAmazon Becker Data CenterAlso: Elk River Technologies site
Developer and teamAmazon Data Services
End userAmazon

The record, newest first

  1. The city administrator said Amazon was suspending development in Minnesota, including Becker. Separately, state regulators had ruled Amazon must show it needs 250 backup diesel generators at the site. (MPR News, May 23, 2025)

  2. Amazon Data Services bought 348 acres from Elk River Technologies, which had bought the land from Xcel in April 2024 for about $7.97 million. (DatacenterDynamics, Nov. 11, 2024)

Conflicts and open questions

  • Separate campus from Microsoft's Becker land. MPR gives about 350 acres.
  • Coordinates approximate.

The full record

Status note
In May 2025 Becker's city administrator said Amazon had told the city it was suspending Minnesota development, Becker included, but would keep the land; Amazon said it was still evaluating the site.
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.