Data center campus · 2007 Schoolmaster Drive, West Creek Corporate Center, north of Engler Blvd. and west of Clover Ridge Drive, Chaska, Carver County, Minnesota

CloudHQ MSP Campus (Chaska)

Approved as of Oct. 23, 2026

CloudHQ plans a data center of about 1.4 million to 1.5 million sq ft and up to 180-200 MW on about 72 acres in Chaska's West Creek Corporate Center. It has preliminary city approval and a conditional use permit, but no final application has been filed. Also known as: Kelzer Property, 2007 Schoolmaster Drive.

Cite← Minnesota data centers
Aitkin CountyAnoka CountyBecker CountyBeltrami CountyBenton CountyBig Stone CountyBlue Earth CountyBrown CountyCarlton CountyCarver CountyCass CountyChippewa CountyChisago CountyClay CountyClearwater CountyCook CountyCottonwood CountyCrow Wing CountyDakota CountyDodge CountyDouglas CountyFaribault CountyFillmore CountyFreeborn CountyGoodhue CountyGrant CountyHennepin CountyHouston CountyHubbard CountyIsanti CountyItasca CountyJackson CountyKanabec CountyKandiyohi CountyKittson CountyKoochiching CountyLac qui Parle CountyLake CountyLake of the Woods CountyLe Sueur CountyLincoln CountyLyon CountyMahnomen CountyMarshall CountyMartin CountyMcLeod CountyMeeker CountyMille Lacs CountyMorrison CountyMower CountyMurray CountyNicollet CountyNobles CountyNorman CountyOlmsted CountyOtter Tail CountyPennington CountyPine CountyPipestone CountyPolk CountyPope CountyRamsey CountyRed Lake CountyRedwood CountyRenville CountyRice CountyRock CountyRoseau CountyScott CountySherburne CountySibley CountySt. Louis CountyStearns CountySteele CountyStevens CountySwift CountyTodd CountyTraverse CountyWabasha CountyWadena CountyWaseca CountyWashington CountyWatonwan CountyWilkin CountyWinona CountyWright CountyYellow Medicine CountyCloudHQ MSP Campus (Chaska) · Approved · 180 MW
Power180MW reported · stated
Floor area1.4e+06sq ft
Site72acres

Who is behind it

ProjectCloudHQ MSP Campus (Chaska)Also: Kelzer Property, 2007 Schoolmaster Drive
Developer and teamCloudHQ
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. Enterprise Minnesota reported CloudHQ was still awaiting final city approvals for the campus, which it said needs up to 200 MW. (Enterprise Minnesota, Feb. 26, 2026)

  2. BridgeTower reported CloudHQ controls the roughly 70-acre site and is cleared to build a 30-ft berm; final site approval and a separate substation process were still ahead, with no groundbreaking date. (BridgeTower Media Newswires (The Daily Reporter), April 15, 2025)

  3. The council voted 4-1 to approve the preliminary site plan and plat for a two-story building of about 1.4 million sq ft, including an exception to the park's 36-ft height limit, after residents raised objections. (City of Chaska, undated; Carver County Local News, Oct. 29, 2024)

  4. The council approved a conditional use permit, after Planning Commission approval on Oct. 11. (City of Chaska, undated)

  5. The council adopted the final AUAR, which studied up to 1.8 million sq ft of development on about 72.3 acres. (City of Chaska, undated; City of Chaska, undated)

  6. DCD reported the council had approved the AUAR order and scoping document for the 72-acre Kelzer property, with a new 300 MW substation planned. (DatacenterDynamics, Aug. 25, 2022)

  7. The Chaska City Council approved the concept plan, a week after the Planning Commission. CloudHQ put its investment at more than $1 billion. (City of Chaska, undated; Star Tribune, Aug. 26, 2022)

Conflicts and open questions

  • Utility resolved by the city's project page: the Minnesota Municipal Power Agency would own and operate the on-site substation, connected to Xcel Energy's transmission line. The 2022 Star Tribune said Xcel was working to acquire the substation land; Carver County Local News (2024) said the project would bring revenue to the city-owned utility.
  • Acreage: about 72.3 acres in the AUAR, 72 acres in DCD, and 70 acres in BridgeTower (2025).
  • Size: about 1.4 million sq ft in two stories (Star Tribune, Carver County Local News); the city page says about 1.5 million sq ft.
  • The city page is undated; status_date is the date it was opened. It says a preliminary system impact study by CloudHQ, MMPA and Xcel was expected to take about six more months.
  • Final approval had not happened: the city lists the final site plan and plat as TBD, and no 2025-2026 council action on it was found.
  • The 2022 plan to build in 2023 slipped; no construction had been reported by Feb. 2026.
  • This site is separate from Stream's 2013 Minneapolis I building at 1708 West Creek Lane (now LightEdge).

The full record

Status note
The council approved the preliminary site plan and plat on Oct. 21, 2024. The city says CloudHQ has not filed a final application, there is no timeline for final review, and the project cannot proceed until a preliminary system impact study is done.
Power note
DCD (2022) reports up to 180 MW; Enterprise Minnesota (2026) says up to 200 MW. The new substation is reported at 300 MW (DCD, Star Tribune 2022) and 200 MW (Carver County Local News 2024).
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.