DataBank MSP1 (Edina)
DataBank's first Twin Cities data center is in Edina. It took over the site in 2013 when it bought VeriSpace and later expanded it to more than 18,000 sq ft. Also known as: DataBank West Twin Cities, former VeriSpace data center.
Who is behind it
The record, newest first
DCD listed MSP1 in Edina and MSP2 in Eagan as DataBank sites with about 106,000 sq ft between them. (DatacenterDynamics, Nov. 2, 2023)
Twin Cities Business reported a $4 million upgrade that would take the Edina center past 18,000 sq ft. (Twin Cities Business, Nov. 23, 2013)
DataBank said it was adding 7,500 sq ft to the Edina site, along with UPS and cooling upgrades. (Patch (Edina), June 6, 2013)
DataBank bought VeriSpace, a carrier-neutral colocation provider with a data center of about 10,000 sq ft in Edina. (Data Center Knowledge, March 18, 2013)
Conflicts and open questions
- No street address was confirmed in an opened primary source or credited reporting; coordinates are set near central Edina.
- DCD (2021, 2023) says MSP1 and MSP2 together have about 106,000 sq ft, most of it at MSP2 (Eagan).
- DataBank's Oct. 2026 release says it runs four Minneapolis-area data centers but does not list them by name; DataBank's MSP1 page was not opened, so evidence stays 'reported'.
The full record
- Status note
- DCD listed MSP1 in Edina among DataBank's operating Minneapolis-area sites in Nov. 2023.
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)