Apple Valley Technology Park
Oppidan and landowner Rockport LLC sought approval for five data center buildings totaling about 1 million sq ft on some 135 acres in Apple Valley; the city turned the plan down in early 2026. Also known as: AV Tech Park.
Who is behind it
Rockport LLC
The record, newest first
The city council adopted a one-year pause on new data center proposals. (Blandin on Broadband (excerpting Sun Thisweek), July 18, 2026)
Acting on the planning commission's recommendation, the council rejected the site plan, preliminary plan and conditional use permit. (DatacenterDynamics, March 30, 2026)
Oppidan withdrew its rezoning application. (DatacenterDynamics, March 30, 2026)
The council voted unanimously against Rockport's comprehensive plan amendment, pointing to water supply, sewer capacity and the property's role in the 2040 plan. (Sun Thisweek / Dakota County Tribune (Hometown Source), Jan. 26, 2026)
The city held a public hearing; the plan needed a conditional use permit and a rezoning from sand and gravel to industrial. Rockport had submitted an AUAR in Dec. 2024, which the city approved. (DatacenterDynamics, Feb. 28, 2025)
Conflicts and open questions
- Acreage: DCD (2026) gives 134 acres; Sun Thisweek gives 135 acres on the east part of a 357-acre Rockport holding.
- Building area: about 1,022,000 sq ft in five buildings plus about 66,000 sq ft of support structures (Sun Thisweek); DCD (2026) gives 1.05 million sq ft. DCD's 2025 story described seven buildings, five of them data centers.
- Sun Thisweek says the comprehensive plan vote came on a Thursday before its Jan. 26, 2026 story, likely Jan. 22; the date is not stated.
- The moratorium source is a blog excerpt of Sun Thisweek; the original Sun Thisweek page could not be opened. City records for the 2026 votes were not located; evidence is news only.
The full record
- Status note
- The city council denied the site plan, preliminary plan and conditional use permit after earlier denying the comprehensive plan change; the city then adopted a one-year data center moratorium.
- Power note
- DCD reported 250-300 MW (Mar. 2026); no record figure found.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)