Data centers · Lee County, North Carolina

Lee County

1 project on record · 1 moratorium or ban action

← Statewide map
Alamance CountyAlexander CountyAlleghany CountyAnson CountyAshe CountyAvery CountyBeaufort CountyBertie CountyBladen CountyBrunswick CountyBuncombe CountyBurke CountyCabarrus CountyCaldwell CountyCamden CountyCarteret CountyCaswell CountyCatawba CountyChatham CountyCherokee CountyChowan CountyClay CountyCleveland CountyColumbus CountyCraven CountyCumberland CountyCurrituck CountyDare CountyDavidson CountyDavie CountyDuplin CountyDurham CountyEdgecombe CountyForsyth CountyFranklin CountyGaston CountyGates CountyGraham CountyGranville CountyGreene CountyGuilford CountyHalifax CountyHarnett CountyHaywood CountyHenderson CountyHertford CountyHoke CountyHyde CountyIredell CountyJackson CountyJohnston CountyJones CountyLee CountyLenoir CountyLincoln CountyMacon CountyMadison CountyMartin CountyMcDowell CountyMecklenburg CountyMitchell CountyMontgomery CountyMoore CountyNash CountyNew Hanover CountyNorthampton CountyOnslow CountyOrange CountyPamlico CountyPasquotank CountyPender CountyPerquimans CountyPerson CountyPitt CountyPolk CountyRandolph CountyRichmond CountyRobeson CountyRockingham CountyRowan CountyRutherford CountySampson CountyScotland CountyStanly CountyStokes CountySurry CountySwain CountyTransylvania CountyTyrrell CountyUnion CountyVance CountyWake CountyWarren CountyWashington CountyWatauga CountyWayne CountyWilkes CountyWilson CountyYadkin CountyYancey CountyPointOne / CyrusOne Lower Moncure Road data center · Proposed · 90 MW
Projects in Lee County
PointOne / CyrusOne Lower Moncure Road data centerPointOne; Helix Ventures90ProposedAug. 17, 202650 MW+

Moratoriums and bans

  1. Aug. 17, 2026 Lee County: Moratorium proposed, rejected. A motion for a 90-day moratorium was not taken up after the county attorney said required notice and hearing had not occurred. (The Rant (Sanford), Aug. 18, 2026)

Updates, newest first

  1. Aug. 17, 2026 PointOne / CyrusOne Lower Moncure Road data center · Commissioners did not adopt a moratorium; the county attorney said required notice and hearing steps had not been taken. (The Rant (Sanford), Aug. 18, 2026)
  2. Aug. 17, 2026 Lee County: Moratorium proposed, rejected · A motion for a 90-day moratorium was not taken up after the county attorney said required notice and hearing had not occurred. (The Rant (Sanford), Aug. 18, 2026)
  3. July 13, 2026 PointOne / CyrusOne Lower Moncure Road data center · About 150 residents asked commissioners for a moratorium, saying the site was presented as a light-industrial business park. (NC Newsline, via Route Fifty, July 16, 2026)
  4. June 8, 2026 PointOne / CyrusOne Lower Moncure Road data center · PointOne and Helix Ventures filed for a 300,000-square-foot, 90 MW facility on 56 acres, phase one of a 430-acre development, with CyrusOne as owner; Central Electric Membership Corp. is building a substation next door. (The Rant (Sanford), June 8, 2026)

Statewide

G.S. 105-164.13(55a) exempts from state sales and use tax the electricity and support equipment (power, cooling, servers, networking) for a qualifying datacenter: one where the Commerce Secretary finds at least $75 million will be invested within five years and that meets a wage standard for its area and provides health insurance to its full-time employees; the older (55) exemption covers eligible internet datacenters investing $250 million in lower-tier counties. (North Carolina General Assembly, Oct. 20, 2026; North Carolina General Assembly, Oct. 20, 2026) Senate Bill 730, the Ratepayer Protection Act, was rewritten in the House to require utilities to contract with large data centers so they cover the cost of serving them; the House passed it 69-44 on June 3, 2026, and the Senate sent it to its Rules Committee on June 8 with no further action recorded. (North Carolina General Assembly, Oct. 20, 2026; Carolina Journal, June 4, 2026) Duke Energy reached a settlement in October 2026 in its rate cases (NCUC dockets E-7 Sub 1329 and E-2 Sub 1380) making an existing tariff mandatory for data centers and other customers that use large amounts of power nearly all the time, with upfront payment for dedicated facilities such as substations; it would not apply to contracts signed on or before June 1, 2026 and needs Utilities Commission approval. (WUNC / WFAE, Oct. 7, 2026; WUNC / WFAE, Oct. 14, 2026) Local moratoriums rest on G.S. 160D-107; Orange County cited it, and a Superior Court judge ruled in September 2026 that Chatham County's moratorium could not halt a project already under way. (Orange County, N.C., April 21, 2026; NC Newsline, Sept. 22, 2026) North Carolina data centers →