Data center project · Iredell County, North Carolina

Compass Datacenters Statesville campus

Approved · Statesville rezoned about 330 acres of farmland for a five-building Compass campus over neighbors' objections; the city's 2026 moratorium exempts it.

← North Carolina data centers
Alamance CountyAlexander CountyAlleghany CountyAnson CountyAshe CountyAvery CountyBeaufort CountyBertie CountyBladen CountyBrunswick CountyBuncombe CountyBurke CountyCabarrus CountyCaldwell CountyCamden CountyCarteret CountyCaswell CountyCatawba CountyChatham CountyCherokee CountyChowan CountyClay CountyCleveland CountyColumbus CountyCraven CountyCumberland CountyCurrituck CountyDare CountyDavidson CountyDavie CountyDuplin CountyDurham CountyEdgecombe CountyForsyth CountyFranklin CountyGaston CountyGates CountyGraham CountyGranville CountyGreene CountyGuilford CountyHalifax CountyHarnett CountyHaywood CountyHenderson CountyHertford CountyHoke CountyHyde CountyIredell CountyJackson CountyJohnston CountyJones CountyLee CountyLenoir CountyLincoln CountyMacon CountyMadison CountyMartin CountyMcDowell CountyMecklenburg CountyMitchell CountyMontgomery CountyMoore CountyNash CountyNew Hanover CountyNorthampton CountyOnslow CountyOrange CountyPamlico CountyPasquotank CountyPender CountyPerquimans CountyPerson CountyPitt CountyPolk CountyRandolph CountyRichmond CountyRobeson CountyRockingham CountyRowan CountyRutherford CountySampson CountyScotland CountyStanly CountyStokes CountySurry CountySwain CountyTransylvania CountyTyrrell CountyUnion CountyVance CountyWake CountyWarren CountyWashington CountyWatauga CountyWayne CountyWilkes CountyWilson CountyYadkin CountyYancey CountyCompass Datacenters Statesville campus · Approved
Status
Approved · as of Sept. 15, 2025
Location
Stamey Farm Road, western Statesville near I-40 · Iredell County
Floor area
1,350,000 sq ft
Land
330 acres
Developer and team
Compass Datacenters
Water
Company described a closed-loop hybrid cooling system
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Sept. 14, 2026 The city's 180-day data center moratorium took effect; it does not affect previously approved data centers. (WBTV, Sept. 14, 2026)
  2. Sept. 15, 2025 Statesville City Council voted 8-0 to rezone about 330 acres owned by the Stamey family for Compass Datacenters' plan of five 270,000-square-foot buildings, each with 40 backup generators; 17 residents spoke against and five in favor. (Governing (The Charlotte Observer, via TNS), Sept. 17, 2025)

Conflicts and open questions

  • Square footage is five buildings of 270,000 square feet each, from the developer's application as reported; no power figure in the sources reviewed.

Have records about this project? Send them to tips@signaldata.org.