Data center project · Mecklenburg County, North Carolina

Digital Realty Moores Chapel Road campus

Approved · Charlotte rezoned 156 acres in west Charlotte for Digital Realty's two-building, up to 400 MW campus, which would be the state's largest by size and power.

← North Carolina data centers
Alamance CountyAlexander CountyAlleghany CountyAnson CountyAshe CountyAvery CountyBeaufort CountyBertie CountyBladen CountyBrunswick CountyBuncombe CountyBurke CountyCabarrus CountyCaldwell CountyCamden CountyCarteret CountyCaswell CountyCatawba CountyChatham CountyCherokee CountyChowan CountyClay CountyCleveland CountyColumbus CountyCraven CountyCumberland CountyCurrituck CountyDare CountyDavidson CountyDavie CountyDuplin CountyDurham CountyEdgecombe CountyForsyth CountyFranklin CountyGaston CountyGates CountyGraham CountyGranville CountyGreene CountyGuilford CountyHalifax CountyHarnett CountyHaywood CountyHenderson CountyHertford CountyHoke CountyHyde CountyIredell CountyJackson CountyJohnston CountyJones CountyLee CountyLenoir CountyLincoln CountyMacon CountyMadison CountyMartin CountyMcDowell CountyMecklenburg CountyMitchell CountyMontgomery CountyMoore CountyNash CountyNew Hanover CountyNorthampton CountyOnslow CountyOrange CountyPamlico CountyPasquotank CountyPender CountyPerquimans CountyPerson CountyPitt CountyPolk CountyRandolph CountyRichmond CountyRobeson CountyRockingham CountyRowan CountyRutherford CountySampson CountyScotland CountyStanly CountyStokes CountySurry CountySwain CountyTransylvania CountyTyrrell CountyUnion CountyVance CountyWake CountyWarren CountyWashington CountyWatauga CountyWayne CountyWilkes CountyWilson CountyYadkin CountyYancey CountyDigital Realty Moores Chapel Road campus · Approved · 400 MW
Status
Approved · as of May 2025
Location
12899 Moores Chapel Road, west Charlotte · Mecklenburg County
Power
400 MW
Up to 400 MW of IT capacity, as previously stated by the company and reported.
Floor area
3,000,000 sq ft
Land
156 acres
Investment
$160 million land purchase (reported)
Developer and team
Digital Realty
Utility
Duke Energy
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Oct. 7, 2026 WUNC reported the project may be among those with Duke Energy contracts signed on or before June 1, 2026, which the proposed large-load tariff would not cover. (WUNC / WFAE, Oct. 7, 2026)
  2. May 2025 City Council approved the rezoning; by October 2025 trees had been cleared and construction timing was not public. (Queen City News (WJZY), via Yahoo News, Oct. 21, 2025)
  3. April 21, 2025 Charlotte City Council heard Digital Realty's request to allow about 3 million square feet of data center space on the 156-acre site, which it bought for $160 million in November 2024. (GovTech (The Charlotte Observer, via TNS), April 23, 2025)

Conflicts and open questions

  • Exact rezoning vote date and petition number not pulled from city records.

Have records about this project? Send them to tips@signaldata.org.