Data center project · Edgecombe County, North Carolina
Energy Storage Solutions Tarboro data center
Denied · Tarboro's council denied a special use permit for a $6.4 billion data center; the developer appealed and later said it would settle and not build there.
- Status
- Denied · as of Oct. 2025
- Location
- Anaconda Road near McNair Road, Tarboro · Edgecombe County
- Land
- 50 acres
- Investment
- $6.4 billion (as reported)
- Developer and team
- Energy Storage Solutions LLC
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- July 14, 2026 The company's president said a settlement with Tarboro had been reached and the company would not build a data center there. (Rocky Mount Telegram, July 14, 2026)
- July 8, 2026 Bisnow, citing the Triangle Business Journal, described the Tarboro plan as a $6.4 billion project on 50 acres still in litigation. (Bisnow, July 8, 2026)
- Nov. 13, 2025 The company asked Edgecombe Superior Court to review the denial, calling it contrary to law and the record. (CBS 17 (WNCN), Nov. 14, 2025)
- Sept. 2025 Tarboro Town Council voted to deny Energy Storage Solutions a special use permit after hearings in August and September; the written order was signed in October. (CBS 17 (WNCN), Nov. 14, 2025)
Conflicts and open questions
- The vote is reported as 6-1 (Rocky Mount Telegram) and 7-1 (the town's order, as quoted by CBS 17).
- About 50 acres; no power figure in the sources reviewed, so it may fall below this tracker's 50 MW scope.
Have records about this project? Send them to tips@signaldata.org.