Data center project · Edgecombe County, North Carolina

Energy Storage Solutions Tarboro data center

Denied · Tarboro's council denied a special use permit for a $6.4 billion data center; the developer appealed and later said it would settle and not build there.

← North Carolina data centers
Alamance CountyAlexander CountyAlleghany CountyAnson CountyAshe CountyAvery CountyBeaufort CountyBertie CountyBladen CountyBrunswick CountyBuncombe CountyBurke CountyCabarrus CountyCaldwell CountyCamden CountyCarteret CountyCaswell CountyCatawba CountyChatham CountyCherokee CountyChowan CountyClay CountyCleveland CountyColumbus CountyCraven CountyCumberland CountyCurrituck CountyDare CountyDavidson CountyDavie CountyDuplin CountyDurham CountyEdgecombe CountyForsyth CountyFranklin CountyGaston CountyGates CountyGraham CountyGranville CountyGreene CountyGuilford CountyHalifax CountyHarnett CountyHaywood CountyHenderson CountyHertford CountyHoke CountyHyde CountyIredell CountyJackson CountyJohnston CountyJones CountyLee CountyLenoir CountyLincoln CountyMacon CountyMadison CountyMartin CountyMcDowell CountyMecklenburg CountyMitchell CountyMontgomery CountyMoore CountyNash CountyNew Hanover CountyNorthampton CountyOnslow CountyOrange CountyPamlico CountyPasquotank CountyPender CountyPerquimans CountyPerson CountyPitt CountyPolk CountyRandolph CountyRichmond CountyRobeson CountyRockingham CountyRowan CountyRutherford CountySampson CountyScotland CountyStanly CountyStokes CountySurry CountySwain CountyTransylvania CountyTyrrell CountyUnion CountyVance CountyWake CountyWarren CountyWashington CountyWatauga CountyWayne CountyWilkes CountyWilson CountyYadkin CountyYancey CountyEnergy Storage Solutions Tarboro data center · Denied
Status
Denied · as of Oct. 2025
Location
Anaconda Road near McNair Road, Tarboro · Edgecombe County
Land
50 acres
Investment
$6.4 billion (as reported)
Developer and team
Energy Storage Solutions LLC
Evidence
News reports; primary records not yet obtained
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. July 14, 2026 The company's president said a settlement with Tarboro had been reached and the company would not build a data center there. (Rocky Mount Telegram, July 14, 2026)
  2. July 8, 2026 Bisnow, citing the Triangle Business Journal, described the Tarboro plan as a $6.4 billion project on 50 acres still in litigation. (Bisnow, July 8, 2026)
  3. Nov. 13, 2025 The company asked Edgecombe Superior Court to review the denial, calling it contrary to law and the record. (CBS 17 (WNCN), Nov. 14, 2025)
  4. Sept. 2025 Tarboro Town Council voted to deny Energy Storage Solutions a special use permit after hearings in August and September; the written order was signed in October. (CBS 17 (WNCN), Nov. 14, 2025)

Conflicts and open questions

  • The vote is reported as 6-1 (Rocky Mount Telegram) and 7-1 (the town's order, as quoted by CBS 17).
  • About 50 acres; no power figure in the sources reviewed, so it may fall below this tracker's 50 MW scope.

Have records about this project? Send them to tips@signaldata.org.