Data center project · Mecklenburg County, North Carolina
PowerHouse Charlotte campus
Approved · A 122-acre PowerHouse Data Centers campus on University City Boulevard was in permitting in early 2025 after a 2023 city approval.
- Status
- Approved · as of Jan. 14, 2025
- Location
- University City Boulevard, northeast Charlotte · Mecklenburg County
- Power
- Not reported
No power figure in the sources opened; trackers list about 300 MW. - Land
- 122 acres
- Developer and team
- PowerHouse Data Centers
- Utility
- Duke Energy
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Oct. 7, 2026 WUNC reported the project may be among those with Duke Energy contracts signed on or before June 1, 2026. (WUNC / WFAE, Oct. 7, 2026)
- Jan. 14, 2025 PowerHouse said its 122-acre Charlotte campus was in the permitting phase. (Data Center Frontier, Jan. 27, 2025)
- Sept. 26, 2023 Charlotte City Council approved the PowerHouse project, according to Baxtel. (Baxtel, Sept. 26, 2023)
Conflicts and open questions
- Approval predates 2024; kept because permitting and utility contracting continued in 2025-26. Construction status not confirmed.