Data center project · Mecklenburg County, North Carolina

PowerHouse Charlotte campus

Approved · A 122-acre PowerHouse Data Centers campus on University City Boulevard was in permitting in early 2025 after a 2023 city approval.

← North Carolina data centers
Alamance CountyAlexander CountyAlleghany CountyAnson CountyAshe CountyAvery CountyBeaufort CountyBertie CountyBladen CountyBrunswick CountyBuncombe CountyBurke CountyCabarrus CountyCaldwell CountyCamden CountyCarteret CountyCaswell CountyCatawba CountyChatham CountyCherokee CountyChowan CountyClay CountyCleveland CountyColumbus CountyCraven CountyCumberland CountyCurrituck CountyDare CountyDavidson CountyDavie CountyDuplin CountyDurham CountyEdgecombe CountyForsyth CountyFranklin CountyGaston CountyGates CountyGraham CountyGranville CountyGreene CountyGuilford CountyHalifax CountyHarnett CountyHaywood CountyHenderson CountyHertford CountyHoke CountyHyde CountyIredell CountyJackson CountyJohnston CountyJones CountyLee CountyLenoir CountyLincoln CountyMacon CountyMadison CountyMartin CountyMcDowell CountyMecklenburg CountyMitchell CountyMontgomery CountyMoore CountyNash CountyNew Hanover CountyNorthampton CountyOnslow CountyOrange CountyPamlico CountyPasquotank CountyPender CountyPerquimans CountyPerson CountyPitt CountyPolk CountyRandolph CountyRichmond CountyRobeson CountyRockingham CountyRowan CountyRutherford CountySampson CountyScotland CountyStanly CountyStokes CountySurry CountySwain CountyTransylvania CountyTyrrell CountyUnion CountyVance CountyWake CountyWarren CountyWashington CountyWatauga CountyWayne CountyWilkes CountyWilson CountyYadkin CountyYancey CountyPowerHouse Charlotte campus · Approved
Status
Approved · as of Jan. 14, 2025
Location
University City Boulevard, northeast Charlotte · Mecklenburg County
Power
Not reported
No power figure in the sources opened; trackers list about 300 MW.
Land
122 acres
Developer and team
PowerHouse Data Centers
Utility
Duke Energy
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Oct. 7, 2026 WUNC reported the project may be among those with Duke Energy contracts signed on or before June 1, 2026. (WUNC / WFAE, Oct. 7, 2026)
  2. Jan. 14, 2025 PowerHouse said its 122-acre Charlotte campus was in the permitting phase. (Data Center Frontier, Jan. 27, 2025)
  3. Sept. 26, 2023 Charlotte City Council approved the PowerHouse project, according to Baxtel. (Baxtel, Sept. 26, 2023)

Conflicts and open questions

  • Approval predates 2024; kept because permitting and utility contracting continued in 2025-26. Construction status not confirmed.

Have records about this project? Send them to tips@signaldata.org.