Data center project · Iredell County, North Carolina

Tract Mooresville Technology Park

Withdrawn · Tract dropped its $30 billion plan for a data center park on land owned by Dale Earnhardt's widow after Mooresville leaders signaled denial.

← North Carolina data centers
Alamance CountyAlexander CountyAlleghany CountyAnson CountyAshe CountyAvery CountyBeaufort CountyBertie CountyBladen CountyBrunswick CountyBuncombe CountyBurke CountyCabarrus CountyCaldwell CountyCamden CountyCarteret CountyCaswell CountyCatawba CountyChatham CountyCherokee CountyChowan CountyClay CountyCleveland CountyColumbus CountyCraven CountyCumberland CountyCurrituck CountyDare CountyDavidson CountyDavie CountyDuplin CountyDurham CountyEdgecombe CountyForsyth CountyFranklin CountyGaston CountyGates CountyGraham CountyGranville CountyGreene CountyGuilford CountyHalifax CountyHarnett CountyHaywood CountyHenderson CountyHertford CountyHoke CountyHyde CountyIredell CountyJackson CountyJohnston CountyJones CountyLee CountyLenoir CountyLincoln CountyMacon CountyMadison CountyMartin CountyMcDowell CountyMecklenburg CountyMitchell CountyMontgomery CountyMoore CountyNash CountyNew Hanover CountyNorthampton CountyOnslow CountyOrange CountyPamlico CountyPasquotank CountyPender CountyPerquimans CountyPerson CountyPitt CountyPolk CountyRandolph CountyRichmond CountyRobeson CountyRockingham CountyRowan CountyRutherford CountySampson CountyScotland CountyStanly CountyStokes CountySurry CountySwain CountyTransylvania CountyTyrrell CountyUnion CountyVance CountyWake CountyWarren CountyWashington CountyWatauga CountyWayne CountyWilkes CountyWilson CountyYadkin CountyYancey CountyTract Mooresville Technology Park · Withdrawn
Status
Withdrawn · as of Aug. 13, 2025
Location
Earnhardt family land, rural Mooresville · Iredell County
Land
400 acres
Investment
$30 billion (developer, as reported)
Developer and team
Tract
Evidence
News reports; primary records not yet obtained
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Aug. 13, 2025 Tract withdrew the proposal, the mayor and the company's engineer said. (NBC News, Aug. 13, 2025)
  2. Aug. 9, 2025 Mooresville's mayor said the board would deny the rezoning because the end user was not known. (WSOC-TV (citing The Charlotte Observer), Aug. 9, 2025)

Conflicts and open questions

  • Acreage differs: about 300 acres (WSOC) or 400 acres (NBC News, WSOC video).

Have records about this project? Send them to tips@signaldata.org.