Tenaska land options along Highway 75, Cass County
Tenaska optioned more than 1,300 acres along Highway 75 for a possible data center project, prompting a county moratorium and a village ban.
Who is behind it
The record, newest first
The Village of Nehawka banned data centers, crypto mining and the plants that power them in its zoning area, which the county moratorium did not cover; landowners near the village had received offers from Tenaska. (WOWT (via 10/11 NOW), Aug. 27, 2026)
Cass County commissioners voted 5-0 for a 12-month moratorium on data center permits and put off proposed regulations to Sept. 22; a farm family across the road from optioned land said it had been offered up to $70,000 an acre. (KLKN-TV, Aug. 11, 2026; KMTV 3 News Now, Aug. 11, 2026)
As the county planning commission met, a residents' group asked for an 18-month pause on permits; WOWT reported Tenaska had optioned more than 1,300 acres along Highway 75. (WOWT, July 13, 2026)
Conflicts and open questions
- The outcome of the county's Sept. 22 regulations vote was not checked.
The full record
- Status note
- No application filed; Cass County adopted a 12-month moratorium on data center permits Aug. 11, 2026, and Nehawka banned data centers in its zoning area.
- Power note
- No power figure; local opponents said technical details were not known.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)