Tenaska land options, northern Gage County (possible Google data center and gas plant)
Omaha-based Tenaska optioned more than 1,000 acres in northern Gage County for a power plant that could serve a data center, which Flatwater linked to a Google proposal for a gas-powered campus in southeast Nebraska. Also known as: Google-Tenaska southeast Nebraska proposal.
Who is behind it
The record, newest first
Supervisors replaced it with a 12-month moratorium on data center permits while planners write rules, settling between the existing eight months and the 18 months recommended. (KLKN-TV, Sept. 16, 2026; Beatrice Daily Sun, Sept. 16, 2026)
The county board approved an eight-month moratorium, KLKN later reported. (KLKN-TV, Sept. 3, 2026)
After a four-hour hearing with about 200 people, the county's planning and zoning commission unanimously recommended an 18-month moratorium; a Tenaska developer said the company was an energy firm seeking large power customers, which could include data centers. (Courier Nebraska, June 17, 2026; KOLN 10/11 NOW, June 16, 2026)
Flatwater Free Press reported documents shared at a private public power district meeting describing a Google data center of 1,000 to 3,000 MW powered by a Tenaska gas plant with carbon capture, and said Tenaska had optioned more than 2,600 acres in southeast Nebraska since December; Gage County supervisor Emily Haxby said Tenaska described a gas plant serving an industrial park in the county's northeast. (Flatwater Free Press, March 13, 2026)
Conflicts and open questions
- Neither Google nor Tenaska confirmed the plan to Flatwater; Tallgrass Energy, named in the documents as a gas supplier, denied any partnership. The link between the Google proposal and the Gage County land is from reporting, not from a filing.
- Acreage: Courier Nebraska reported more than 1,000 acres; Supervisor Haxby said she understood Tenaska might seek 1,000 to 3,000 acres.
The full record
- Status note
- No permit application has been filed; the county board adopted a 12-month moratorium on data center permits Sept. 16, 2026.
- Power note
- Documents described by Flatwater put the Google proposal's data center at 1,000 to 3,000 MW, but they did not name a site; no figure has been tied to this land in a public record.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)