Data center project · Union County, New Jersey
CoreWeave data center at the NEST campus (former Merck headquarters), Kenilworth
Under construction · CoreWeave's conversion of a former Merck laboratory in Kenilworth into a planned 250 MW AI data center, the sole recipient of New Jersey's AI data center tax credit. Also known as: 11 NEST Drive, Northeast Science & Technology Center.
- Status
- Under construction · as of Sept. 2025
- Location
- 11 NEST Drive, on the NEST campus at 2000 Galloping Hill Road, Kenilworth · Union County
- Status note
- Construction began in mid-September 2025, per RE-NJ; operation is expected in early 2027.
- Power
- 250 MW
250 MW is the planned capacity reported by RE-NJ; Inside Climate News quotes CoreWeave that the full campus could need up to 250 MW. The planning board minutes give no power figure. - Floor area
- 392,600 sq ft
- Land
- 36 acres
- Investment
- About $1.76 billion by NJEDA's figure (reported as nearly $1.8 billion); CoreWeave had first announced $1.2 billion with its 2024 lease, and paid $322 million in 2025 for the building and 27 adjacent acres
- Developer and team
- CoreWeave
- End user
- CoreWeave
- Utility
- Not named in the sources reviewed; Commercial Observer reports the campus has its own 50 MW substation
- Incentives
- $250 million Next New Jersey Program - AI tax credit approved by the NJEDA board on Nov. 12, 2025 ($50 million a year over five years of a 10-year commitment, for 143 jobs); the only award the program made
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- April 30, 2026 The Leader reported residents raising concerns about the power grid, safety and the environment. (The Leader (Westfield), April 30, 2026; NJ Spotlight News, July 21, 2026)
- Nov. 12, 2025 The NJEDA board approved a $250 million Next New Jersey Program - AI tax credit for CoreWeave in Kenilworth. (New Jersey Economic Development Authority, Nov. 12, 2025; New Jersey Economic Development Authority, Aug. 2026; Real Estate NJ, Nov. 25, 2025; Inside Climate News, Feb. 26, 2026)
- Aug. 5, 2025 Commercial Observer reported CoreWeave bought the building and 27 adjacent acres from the owners' venture for $322 million. (Commercial Observer, Aug. 5, 2025)
- May 15, 2025 The Kenilworth Planning Board voted 8-0 to approve CoreWeave's site plan (Application #25-003) to convert the lab building on a 36-acre lot into a data center, with 31 generators and a chiller yard. (Borough of Kenilworth Planning Board, May 15, 2025)
- Oct. 24, 2024 CoreWeave signed a long-term lease for the 280,000-square-foot Building 11 at the NEST campus owned by an Onyx Equities and Machine Investment Group venture. (NJBIZ, Oct. 24, 2024)
Conflicts and open questions
- Square footage differs by stage: the planning board testimony described about 247,000 square feet across the existing building; RE-NJ, citing NJEDA, gives 392,600 square feet including 108,100 of new construction.
Have records about this project? Send them to tips@signaldata.org.