Data center project · Clark County, Nevada
Copia Digital Bergen Data Center
Proposed · A Copia data center proposed on federal land near Apex, tied by PUCN filings to the Harry Allen substation.
- Status
- Proposed · as of Jan. 27, 2026
- Location
- Federal land near the Harry Allen substation, north of Las Vegas · Clark County
- Power
- Not reported
No figure in the sources reviewed. - Developer and team
- Copia Digital / Copia Power
- Utility
- NV Energy grid via Harry Allen substation; Copia is also permitting a gas plant near Apex
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- March 12, 2026 The Indy reported Copia was permitting a gas plant and batteries northeast of Las Vegas near Apex. (The Nevada Independent, March 12, 2026)
- Jan. 27, 2026 Copia Digital notified the PUCN (docket 26-01035) of a federal application for two transmission lines of up to 500 kV linking the Bergen Data Center to the Harry Allen substation. (Public Utilities Commission of Nevada, Oct. 20, 2026)
- Sept. 24, 2024 Copia GDC, LLC notified the PUCN (docket 24-09023) of a federal application for a 500 MW gas plant, gen-tie, pipeline and batteries on federal land in Clark County. (Public Utilities Commission of Nevada, Oct. 20, 2026)
Conflicts and open questions
- Whether the 500 MW gas plant in docket 24-09023 serves Bergen is not confirmed.
Have records about this project? Send them to tips@signaldata.org.