| Stream data center campus at STAMP (Project Double Reed) | Stream U.S. Data Centers | 500 | Proposed | July 15, 2026 | 50 MW+ |
Updates, newest first
- Sept. 30, 2026 Stream data center campus at STAMP (Project Double Reed) · NYISO's queue lists two 300 MW data center load requests for the STAMP substation by GCEDC, marked under construction. (New York Independent System Operator (NYISO), Sept. 30, 2026)
- July 15, 2026 Stream data center campus at STAMP (Project Double Reed) · Investigative Post reported it was unclear whether the governor's permit pause applies, since DEC had not yet accepted the project's stormwater plans; GCEDC had not voted on the incentives. (Investigative Post, July 15, 2026)
- July 14, 2026 Stream data center campus at STAMP (Project Double Reed) · The Tonawanda Seneca Nation, the Sierra Club and a town resident sued in State Supreme Court to void the 2012 zoning agreement between the Town of Alabama and GCEDC that governs the site. (Sierra Club Niagara Group, July 14, 2026; Investigative Post, July 15, 2026)
- April 16, 2026 Stream data center campus at STAMP (Project Double Reed) · GCEDC held a second public hearing in Alabama; opponents included the Tonawanda Seneca Nation and environmental groups, while building-trades unions spoke in favor. (The Batavian, April 17, 2026)
- March 18, 2026 Stream data center campus at STAMP (Project Double Reed) · Investigative Post reported the requested tax breaks at about $1.46 billion, mostly sales tax on equipment, for about 125 permanent jobs. (Investigative Post, March 18, 2026)
- March 2026 Stream data center campus at STAMP (Project Double Reed) · A revised application raised the planned investment to $19.46 billion, with 2.2 million sq ft in three two-story buildings. (DatacenterDynamics, March 9, 2026)
- Dec. 18, 2025 Stream data center campus at STAMP (Project Double Reed) · The GCEDC board voted to act as lead agency for the environmental review of the expanded project; the Tonawanda Seneca Nation had asked the state DEC to take that role instead. (The Batavian, Dec. 19, 2025)
- Sept. 2025 Stream data center campus at STAMP (Project Double Reed) · Stream withdrew the first plan; GCEDC later rescinded its approvals after Stream announced a larger project. (The Batavian, Dec. 19, 2025)
- March 6, 2025 Stream data center campus at STAMP (Project Double Reed) · The Genesee County Economic Development Center (GCEDC) approved Stream's first, smaller plan: 900,000 sq ft and 250 MW on 59 acres. (The Batavian, Dec. 19, 2025)
Statewide
Executive Order 62 (July 14, 2026) tells DEC to hold all incomplete discretionary permit applications for building or expanding data centers that use, or can use, 50 MW or more until the Department of Public Service finishes a statewide environmental impact statement; local permits are not covered, and the order sets no end date. (Office of the Governor of New York, July 14, 2026; Hodgson Russ LLP, July 16, 2026) Responsible Data Center Development Act (S10642/A11560): passed the Senate 43-17 on June 4, 2026 and the Assembly; it would pause state permits for data centers of 20 MW or more for a year, require separate utility rate classes and renewable targets; not yet signed or vetoed as of Oct. 18, 2026. (New York State Senate, June 4, 2026; WBNG, June 5, 2026) PSC Case 26-E-0045 (Energize NY Development) is the large-load interconnection proceeding, opened Feb. 12, 2026 under a beneficiary-pays approach; on Sept. 17, 2026 the PSC issued a draft scope for the data center environmental impact statement, with comments due Oct. 20, 2026. (New York State Public Service Commission (copy hosted by RTO Insider), Feb. 12, 2026; New York State Department of Public Service, Sept. 17, 2026; Office of the Governor of New York, July 14, 2026) Tax breaks: a 2000 state law gives internet data centers state and local sales tax breaks, and local IDAs grant sales, property and mortgage-tax abatements; the governor says she will seek a ban on these breaks for data centers of 50 MW or more in the next budget (no bill number yet). (Investigative Post, July 21, 2026; Spectrum News, Sept. 18, 2026) NYISO load queue: the state reports nearly 12 GW of data center load requests as of May 2026; the Sept. 30, 2026 queue lists data center requests across St. Lawrence, Niagara, Dutchess, Suffolk and other counties. (Office of the Governor of New York, July 14, 2026; New York Independent System Operator (NYISO), Sept. 30, 2026) New York data centers →