Data center project · Genesee County, New York
Stream data center campus at STAMP (Project Double Reed)
Proposed · A three-building, roughly 500 MW campus that Stream wants to build at the state-backed STAMP park, seeking about $1.46 billion in tax breaks from the county IDA. Also known as: Project Double Reed, Western New York Science, Technology and Advanced Manufacturing Park.
- Status
- Proposed · as of July 15, 2026
- Location
- STAMP industrial park, Town of Alabama · Genesee County
- Status note
- No GCEDC vote on the incentive package or final SEQR findings found as of Oct. 18, 2026; the state permit pause may apply.
- Power
- 500 MW
About 500 MW per GCEDC and Stream; GCEDC says STAMP has a 600 MW allocation from NYPA hydropower. - Floor area
- 2,200,000 sq ft
- Land
- 130 acres
- Investment
- $19.46 billion (revised application, March 2026)
- Developer and team
- Stream U.S. Data Centers
- End user
- Unnamed Fortune 50 company (per DCD)
- Utility
- New York Power Authority hydropower allocation; National Grid/NYPA interconnection at the STAMP substation (NYISO queue 0580, 1484)
- Water
- About 20,000 gallons a day of fresh water by new pipeline (Sierra Club figure)
- Incentives
- Requested from GCEDC: about $1.43 billion in sales tax exemptions and $31 million in mortgage-tax exemptions, plus a PILOT of about $285 million to local governments (Investigative Post, The Batavian); not yet approved.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Sept. 30, 2026 NYISO's queue lists two 300 MW data center load requests for the STAMP substation by GCEDC, marked under construction. (New York Independent System Operator (NYISO), Sept. 30, 2026)
- July 15, 2026 Investigative Post reported it was unclear whether the governor's permit pause applies, since DEC had not yet accepted the project's stormwater plans; GCEDC had not voted on the incentives. (Investigative Post, July 15, 2026)
- July 14, 2026 The Tonawanda Seneca Nation, the Sierra Club and a town resident sued in State Supreme Court to void the 2012 zoning agreement between the Town of Alabama and GCEDC that governs the site. (Sierra Club Niagara Group, July 14, 2026; Investigative Post, July 15, 2026)
- April 16, 2026 GCEDC held a second public hearing in Alabama; opponents included the Tonawanda Seneca Nation and environmental groups, while building-trades unions spoke in favor. (The Batavian, April 17, 2026)
- March 18, 2026 Investigative Post reported the requested tax breaks at about $1.46 billion, mostly sales tax on equipment, for about 125 permanent jobs. (Investigative Post, March 18, 2026)
- March 2026 A revised application raised the planned investment to $19.46 billion, with 2.2 million sq ft in three two-story buildings. (DatacenterDynamics, March 9, 2026)
- Dec. 18, 2025 The GCEDC board voted to act as lead agency for the environmental review of the expanded project; the Tonawanda Seneca Nation had asked the state DEC to take that role instead. (The Batavian, Dec. 19, 2025)
- Sept. 2025 Stream withdrew the first plan; GCEDC later rescinded its approvals after Stream announced a larger project. (The Batavian, Dec. 19, 2025)
- March 6, 2025 The Genesee County Economic Development Center (GCEDC) approved Stream's first, smaller plan: 900,000 sq ft and 250 MW on 59 acres. (The Batavian, Dec. 19, 2025)
Conflicts and open questions
- Site size is given as 90 acres (Investigative Post, Sierra Club) and 130 acres (DCD, The Batavian); both are reported.
- Total tax-break figure has risen with each application: $472 million, about $800 million, then about $1.46 billion.
Have records about this project? Send them to tips@signaldata.org.