Data center project · Niagara County, New York
Digi Power X North Tonawanda AI conversion
Paused by moratorium · A plan to convert a bitcoin mine at a gas plant into an AI data center, halted by the city's extended moratorium.
- Status
- Paused by moratorium · as of June 16, 2026
- Location
- 1070 Erie Ave., North Tonawanda (Fortistar plant) · Niagara County
- Power
- 60 MW
About 60 MW used for crypto mining today, with room for about 60 MW more (DCD). - Floor area
- 80,000 sq ft
- Developer and team
- Digi Power X
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- June 2026 Digi Power X filed a proposal for an 80,000 sq ft AI building; the Common Council then extended its data center moratorium by a year. (DatacenterDynamics, June 18, 2026; The Energy Mag, June 18, 2026)
Conflicts and open questions
- NYISO lists a 50.2 MW Digihost Technologies load in service at Walck Rd. 115 kV; whether it is this site was not confirmed.