Data center project · Niagara County, New York
Niagara Digital Campus
Proposed · A downtown Niagara Falls campus first floated in 2022 that remains in NYISO's facilities-study stage.
- Status
- Proposed · as of Sept. 30, 2026
- Location
- Rainbow and John B. Daly boulevards, Niagara Falls · Niagara County
- Power
- 140 MW
- Floor area
- 600,000 sq ft
- Investment
- $1.5 billion (2022 announcement)
- Developer and team
- Niagara Falls Redevelopment (Milstein Properties); Urbacon
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- April 9, 2024 The developer filed a 140 MW data center load request, now in facilities study. (New York Independent System Operator (NYISO), Sept. 30, 2026)
- June 29, 2022 Niagara Falls Redevelopment unveiled a 135 MW, $1.5 billion plan; the mayor questioned whether zoning allowed it. (DatacenterDynamics, June 29, 2022)