Data center project · Greene County, New York
NY-Route 9W Load Center
Withdrawn · A 1,000 MW load request in Greene County that NYISO lists as withdrawn.
- Status
- Withdrawn · as of Sept. 30, 2026
- Location
- Near the Leeds 345 kV substation · Greene County
- Power
- 1,000 MW
- Developer and team
- NY-Route 9W LLC
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Jan. 7, 2026 NY-Route 9W LLC filed a 1,000 MW load request at the Leeds substation; the queue gives no end use and now marks it withdrawn. (New York Independent System Operator (NYISO), Sept. 30, 2026)
Conflicts and open questions
- End use is blank in the queue; it is included because of its size and is not confirmed as a data center.