Data center project · St. Lawrence County, New York
St. Lawrence Infrastructure data center
Proposed · Two grid requests totaling 2,795 MW, the largest data center load in New York's queue; no local filing was found.
- Status
- Proposed · as of Sept. 30, 2026
- Location
- Massena area (NYPA Moses-Massena and Haverstock-Adirondack lines) · St. Lawrence County
- Status note
- Grid interconnection request only; no local application or public proposal found.
- Power
- 2,795 MW
- Developer and team
- St. Lawrence Infrastructure, LLC
- Utility
- New York Power Authority
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Sept. 2, 2025 St. Lawrence Infrastructure filed two AI data center load requests with NYISO, for 860 MW and 1,935 MW. (New York Independent System Operator (NYISO), Sept. 30, 2026)
Have records about this project? Send them to tips@signaldata.org.