Data center project · St. Lawrence County, New York
New York State Artificial Intelligence Data Center
Proposed · A 300 MW AI data center grid request by ZeroC near Massena.
- Status
- Proposed · as of Sept. 30, 2026
- Location
- Massena area · St. Lawrence County
- Status note
- Grid interconnection request only; no local application found.
- Power
- 300 MW
- Developer and team
- ZeroC Data Centers, LLC
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- March 14, 2025 ZeroC filed a 300 MW AI data center load request on NYPA's Haverstock-Adirondack line; an earlier 300 MW request at the Dennison substation is marked withdrawn. (New York Independent System Operator (NYISO), Sept. 30, 2026)