Data center project · Washington County, Oregon
Aligned Data Centers PDX campus (PDX-01 and PDX-02), Hillsboro
Under construction · A two-building, 108 MW Aligned campus on 27 acres in north Hillsboro; its second phase is caught by the city's 2026 moratorium.
- Status
- Under construction · as of Oct. 18, 2023
- Location
- NE 30th Ave. and NE Evergreen Rd., Hillsboro · Washington County
- Status note
- Ground was broken on PDX-01 in 2023; the PDX-02 pre-application filed in July 2026 is not exempt from Hillsboro's moratorium, the city says.
- Power
- 108 MW
Aligned's plan: 72 MW of critical capacity for PDX-01 and 36 MW for PDX-02. - Land
- 27 acres
- Developer and team
- Aligned Data Centers
- Utility
- Portland General Electric
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Aug. 12, 2026 DCD reported Aligned had filed a pre-application for PDX-02 before the moratorium; the city's project manager said a pre-application is not a formal application and is not exempt. (DatacenterDynamics, Aug. 12, 2026)
- Oct. 18, 2023 DCD reported Aligned had broken ground on PDX-01, planned as twelve 6 MW data halls. (DatacenterDynamics, Oct. 18, 2023)
- Jan. 10, 2023 Aligned announced a 108 MW, two-building campus on 27 acres at NE 30th Ave. and NE Evergreen Rd. (DatacenterDynamics, Jan. 10, 2023)
Conflicts and open questions
- Whether PDX-01 is now operating was not found in the sources reviewed.
Have records about this project? Send them to tips@signaldata.org.