Data center project · Crook County, Oregon
Apple Prineville data center
Operating · Apple's Prineville data center on a 160-acre site, kept as operating context.
- Status
- Operating · as of May 9, 2024
- Location
- Prineville · Crook County
- Power
- Not reported
No power figure from Apple in the sources reviewed. - Land
- 160 acres
- Developer and team
- Apple
- Water
- Apple funded Prineville's first aquifer injection well in 2019 with an $8.7 million grant.
- Incentives
- Reported in 2012 as a deal with Prineville and Crook County exempting most property taxes, with at least $250 million of investment committed; Apple had not confirmed it. Later terms were not reviewed.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- May 9, 2024 The Bulletin reported Apple paid for the city's first aquifer storage well, completed in 2019. (The Bulletin (Bend), May 9, 2024)
- April 23, 2012 DCD, citing The Oregonian, reported Apple's tax break for a 160-acre site with at least $250 million of investment. (DatacenterDynamics, April 23, 2012)
Have records about this project? Send them to tips@signaldata.org.