Data center project · Washington County, Oregon
Flexential Hillsboro data centers
Operating · Flexential's four Hillsboro colocation buildings, with GPU-cloud provider CoreWeave reported as a tenant in 2023, kept as operating context.
- Status
- Operating · as of Oct. 2023
- Location
- Hillsboro (several buildings; addresses not in the sources) · Washington County
- Power
- 80 MW
DCD's 2023 approximate total (close to 80 MW) for Flexential's four Hillsboro buildings. - Floor area
- 800,000 sq ft
- Developer and team
- Flexential
- End user
- CoreWeave was reported in 2023 to be leasing Flexential space in Hillsboro.
- Utility
- Portland General Electric
- Incentives
- Flexential is among the 2026 Hillsboro enterprise zone applicants whose approvals are challenged in court; amounts were not reported.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- June 23, 2026 Flexential and CoreWeave were named among the 2026 enterprise zone applicants in the court challenge. (OPB, June 23, 2026; KATU, June 25, 2026)
- Oct. 11, 2023 DCD reported CoreWeave would lease Flexential capacity in Hillsboro and put Flexential's four Hillsboro sites at about 800,000 square feet and close to 80 MW. (DatacenterDynamics, Oct. 11, 2023)
Conflicts and open questions
- The map point is a generic north Hillsboro location, not a building address.
Have records about this project? Send them to tips@signaldata.org.