Data center project · Washington County, Oregon
QTS Hillsboro campus
Operating · QTS's five-building Hillsboro campus announced in 2020, kept as operating context for the Hillsboro cluster.
- Status
- Operating · as of 2020
- Location
- Hillsboro (site address not given in the source) · Washington County
- Status note
- QTS said the first phase would open in mid-2020; current build-out was not found.
- Power
- 250 MW
QTS's 2020 figure for gross power capacity at full build-out (more than 250 MW), not IT load. - Floor area
- 1,500,000 sq ft
- Land
- 92 acres
- Developer and team
- QTS Data Centers
- Utility
- Portland General Electric
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Feb. 25, 2020 QTS announced a 92-acre Hillsboro campus planned for five data centers with about 1.5 million gross square feet and gross power capacity above 250 MW, the first building at 27 MW. (Lightwave, Feb. 25, 2020)
Conflicts and open questions
- Whether QTS North HIL3 is an expansion of this campus or a separate site was not established from the sources reviewed.
Have records about this project? Send them to tips@signaldata.org.