Data center project · Lackawanna County, Pennsylvania
Project Gravity (Archbald 25 Developer LLC)
Proposed · A seven-building campus on 186 acres of mine-scarred land in Archbald, dropped from the state's Fast Track permitting program for not sharing project details.
- Status
- Proposed · as of April 27, 2026
- Location
- Between Business Route 6 and Eynon-Jermyn Road, Archbald Borough · Lackawanna County
- Status note
- Filed under Archbald's older zoning, so it skipped a conditional use hearing; still needs final borough land development approval. Removed from the state's Fast Track program.
- Floor area
- 945,000 sq ft
- Land
- 186 acres
- Investment
- About $5 billion (developer filing with the state, reported)
- Developer and team
- Archbald 25 Developer LLC
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Oct. 20, 2026 The state Department of Environmental Protection's data center permit tracker lists 5 environmental permit or authorization entries for the project: 2 pending, 3 not yet submitted. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026; Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
- April 27, 2026 The Shapiro administration removed Project Gravity from Fast Track, citing the developer's lack of responsiveness and transparency. (WVIA News, May 1, 2026)
- Oct. 24, 2025 Earliest environmental permit application listed for the project on DEP's data center permit tracker submitted. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026; Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
- Sept. 22, 2025 The state Office of Transformation and Opportunity accepted the project into its Fast Track permitting program. (WVIA News, May 1, 2026)
Conflicts and open questions
- Building size differs by source: WVIA gives about 135,000 sq ft each (945,000 total, used here); WBRE/WYOU gives about 276,000 sq ft each.
- The removal date is inferred from WVIA's report that the notice was sent the Monday before May 1, 2026.
Have records about this project? Send them to tips@signaldata.org.