Data center project · Lackawanna County, Pennsylvania
Project Scott (Archbald I LLC, Provident Realty Advisors)
Denied · Archbald council rejected an 18-building data center application on the last day before it would have been approved by default; the developer appealed.
- Status
- Denied · as of March 27, 2026
- Location
- Archbald Borough · Lackawanna County
- Status note
- Borough council denied the conditional use; the developer filed a land use appeal on April 24, 2026.
- Developer and team
- Provident Realty Advisors (through Archbald I LLC)
- Evidence
- Primary public records
- Size class
- Under 50 MW (outside main scope; kept for completeness)
Updates, newest first
- Oct. 20, 2026 DEP's tracker lists the project as proposed, with no permit applications received. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
- April 24, 2026 Archbald I LLC took the council's decision to court in a land use appeal. (Resilience (from CASSE), June 16, 2026)
- March 27, 2026 At a special meeting, council voted down the 18-building conditional use application before a deemed-approval deadline. (DeSmog, March 31, 2026; WBRE/WYOU 28/22 News, March 28, 2026)
- Nov. 24, 2025 Archbald council voted 5-2 to create a data center overlay district requiring council approval of data centers. (DeSmog, March 31, 2026; Resilience (from CASSE), June 16, 2026)
- Oct. 2025 The developer's first application covered 22 buildings on two sites. (DeSmog, March 31, 2026)
Conflicts and open questions
- Building count and acreage not given in a primary record; power not reported.
- DeSmog did not report the vote tally; a later Resilience/CASSE piece said 5-0.
- Sources differ on the denied application: DeSmog says 18 buildings (the October 2025 filing had 22 on two sites); WBRE/WYOU describes 22 buildings on two campuses. DEP lists Project Scott (Patrinely-Provident) separately from an unnamed Archbald I LLC / Archbald II LLC entry.
Have records about this project? Send them to tips@signaldata.org.