Data center project · Luzerne County, Pennsylvania

Amazon Web Services Salem Township campus (former Talen Cumulus campus, next to Susquehanna nuclear plant)

Approved · Amazon is expanding the data center campus it bought from Talen Energy beside the Susquehanna nuclear plant, on land Salem Township rezoned for up to 15 data center buildings. Also known as: Cumulus data center campus, Salem Township Data Center Development.

← Pennsylvania data centers
Adams CountyAllegheny CountyArmstrong CountyBeaver CountyBedford CountyBerks CountyBlair CountyBradford CountyBucks CountyButler CountyCambria CountyCameron CountyCarbon CountyCentre CountyChester CountyClarion CountyClearfield CountyClinton CountyColumbia CountyCrawford CountyCumberland CountyDauphin CountyDelaware CountyElk CountyErie CountyFayette CountyForest CountyFranklin CountyFulton CountyGreene CountyHuntingdon CountyIndiana CountyJefferson CountyJuniata CountyLackawanna CountyLancaster CountyLawrence CountyLebanon CountyLehigh CountyLuzerne CountyLycoming CountyMcKean CountyMercer CountyMifflin CountyMonroe CountyMontgomery CountyMontour CountyNorthampton CountyNorthumberland CountyPerry CountyPhiladelphia CountyPike CountyPotter CountySchuylkill CountySnyder CountySomerset CountySullivan CountySusquehanna CountyTioga CountyUnion CountyVenango CountyWarren CountyWashington CountyWayne CountyWestmoreland CountyWyoming CountyYork CountyAmazon Web Services Salem Township campus (former Talen Cumulus campus, next to Susquehanna nuclear plant) · Approved · 960 MW
Status
Approved · as of June 9, 2025
Location
Salem Township, near Berwick, beside the Susquehanna Steam Electric Station (Mingle Inn Road area) · Luzerne County
Status note
Zoned for data centers in 2024 and DEP has finished its review of the first set of permits; a second set of applications for the campus is pending. The original Talen-built building was already operating when Amazon bought it.
Power
960 MW
960 MW is the campus capacity Talen gave when it sold the site; Amazon's June 2025 power deal with Talen is for up to 1,920 MW for Amazon's Pennsylvania data centers, ramping up through 2032.
Land
1,600 acres
Investment
Amazon paid $650 million for Talen's campus in March 2024; part of Amazon's announced $20 billion Pennsylvania data center investment (June 2025)
Developer and team
Amazon Web Services (through Amazon Data Services, Inc.)
End user
Amazon Web Services
Utility
Talen Energy (Susquehanna nuclear plant) as power seller; PPL Electric Utilities for transmission and delivery
Incentives
Salem Township approved a 10-year, 70% LERTA property tax abatement (reported by DCD, 2024)
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.

Updates, newest first

  1. Oct. 20, 2026 The state Department of Environmental Protection's data center permit tracker lists 34 environmental permit or authorization entries for the project: 25 issued, 5 pending, 4 not yet submitted. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026; Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
  2. Aug. 18, 2026 First of a second set of state permit applications for the campus (listed separately on DEP's tracker) submitted. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026; Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
  3. June 11, 2025 Talen announced a deal to sell Amazon up to 1,920 MW from Susquehanna through 2042, delivered through the grid rather than behind the meter. (Utility Dive, June 11, 2025)
  4. June 9, 2025 Gov. Shapiro and Amazon announced at least $20 billion of Amazon data center investment in Pennsylvania, naming Salem Township and Falls Township as the first sites. (WVIA News, June 9, 2025)
  5. Nov. 2024 Federal regulators (FERC) rejected an amended interconnection agreement that would have let the nuclear plant sell more power directly to the co-located Amazon campus. (Utility Dive, June 11, 2025)
  6. June 11, 2024 Earliest environmental permit application listed for the project on DEP's data center permit tracker submitted. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026; Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
  7. May 30, 2024 Salem Township supervisors voted 3-0 to put nearly 1,600 acres into a new data center overlay district; Amazon plans up to 15 buildings over about ten years. (Data Center Dynamics, May 30, 2024)
  8. March 2024 Amazon bought Talen Energy's Cumulus data center campus next to the Susquehanna nuclear plant for $650 million. (WVIA News, June 9, 2025; Data Center Dynamics, May 30, 2024)

Conflicts and open questions

  • DEP's tracker lists the campus twice: one entry marked 'DEP Review Complete' and a later entry with applications pending.
  • The Times Leader (Aug. 22, 2026) reported the campus could eventually hold up to 20 data centers on about 1,200 acres; that figure comes from a developer presentation.

Have records about this project? Send them to tips@signaldata.org.