Data center project · Indiana County, Pennsylvania
Homer City Energy Campus: Amazon data centers and Homer City gas plant
Proposed · Amazon has filed plans for 39 data centers on about 2,200 acres at the former Homer City coal plant, where a 4.4 GW gas plant is planned to power them. Also known as: Homer City Redevelopment.
- Status
- Proposed · as of Aug. 27, 2026
- Location
- Former Homer City Generating Station, Center and Blacklick townships · Indiana County
- Status note
- Amazon filed a master land development plan with the Indiana County planning office; the gas plant has its state air permit, which is under appeal.
- Power
- Not reported
No data center load published; the planned on-site gas plant is 4.4 to 4.5 GW. - Land
- 2,200 acres
- Investment
- $10 billion for the energy campus (developer figure, 2025); Amazon has not published a figure
- Developer and team
- Amazon Web Services (through Amazon Data Services, Inc.); Homer City Redevelopment
- End user
- Amazon Web Services
- Utility
- FirstEnergy, backed by the on-site gas plant
- Water
- Non-contact cooling water from existing withdrawal rights, returned to the station (Amazon filing)
- Incentives
- Amazon's filing says it does not expect to seek property tax reductions
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Oct. 20, 2026 DEP's tracker lists both an Amazon data center and a Homer City Redevelopment data center at the site as proposed, with no permit applications received. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
- Aug. 27, 2026 Amazon Data Services filed a project narrative with Indiana County planning for 39 two-story data centers on six sites, built from December 2026 to 2036. (Indiana County Office of Planning and Development, Aug. 27, 2026)
- Dec. 17, 2025 Clean Air Council, PennFuture and Sierra Club appealed the air permit to the state Environmental Hearing Board. (PennFuture, Dec. 17, 2025)
- Nov. 18, 2025 DEP issued the air plan approval (No. 32-00457A) for the Homer City gas plant, seven GE Vernova turbines of up to 4.4 GW. (Homer City Generation (Business Wire), Nov. 20, 2025; Technical.ly, Nov. 19, 2025; PennFuture, Dec. 17, 2025)
Conflicts and open questions
- Dates inferred: the Nov. 18, 2025 air approval date comes from Technical.ly's Nov. 19 story ('yesterday'); the approval number is from PennFuture's appeal release. The Amazon narrative carries no date; Aug. 27, 2026 is from its file name and PDF creation date.