Data center project · Luzerne County, Pennsylvania
Project Hazelnut (NorthPoint Development)
Denied · NorthPoint's 15-building campus on about 1,280 acres in Hazle Township was a state Fast Track project but was denied by the township and remains in court.
- Status
- Denied · as of Nov. 2025
- Location
- Hazle Township, near Humboldt Industrial Park off Route 924 and I-81 · Luzerne County
- Status note
- Hazle Township denied land development approval in November 2025; a county judge sent NorthPoint's appeal back toward the zoning hearing board in late May 2026. DEP still lists permits under review.
- Power
- Not reported
No power figure published in the sources reviewed. - Land
- 1,280 acres
- Developer and team
- NorthPoint Development (through NP Hazleton Logistics)
- Water
- Air-cooled design; developer proposed using treated wastewater from the West Hazleton plant
- Incentives
- Hazle Township and the Hazleton Area School District approved LERTA property tax breaks; NorthPoint asked Luzerne County for one in 2025 (reported). NorthPoint later offered a $30 million community fund (May 2026).
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Oct. 20, 2026 The state Department of Environmental Protection's data center permit tracker lists 17 environmental permit or authorization entries for the project: 13 issued, 2 pending, 2 not yet submitted. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026; Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
- June 8, 2026 Hazle Township declared its zoning ordinance invalid on data centers, starting a 180-day pause on new data center applications while it writes rules. (Times Leader, June 8, 2026)
- May 19, 2026 NorthPoint announced a $30 million community fund to offset possible local utility rate increases, while appealing the denial in county court. (Dallas Post (Times Leader), May 19, 2026)
- May 2026 A Luzerne County judge denied NorthPoint's appeal, agreeing with the township that the case belongs before the zoning hearing board. (Times Leader, June 8, 2026; Food & Water Watch, June 9, 2026; Inside Climate News, July 2, 2026)
- Nov. 2025 Hazle Township supervisors denied NorthPoint's land development application. (Times Leader, June 8, 2026; Dallas Post (Times Leader), May 19, 2026)
- Feb. 18, 2025 A Luzerne County Council committee advanced NorthPoint's request for a 10-year county property tax break on the 15-building campus. (Dallas Post (Times Leader), Feb. 18, 2025)
- Dec. 3, 2024 Earliest environmental permit application listed for the project on DEP's data center permit tracker submitted. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026; Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
Conflicts and open questions
- Later national coverage (Sept.-Oct. 2026) described a NorthPoint offer of $10,000 per household; not checked against a primary record here.