Data center project · Luzerne County, Pennsylvania
QTS Salem campus
Proposed · QTS bought about 1,700 acres from nearly 100 landowners in Salem Township for a campus of roughly 12 to 17 data center buildings. Also known as: Salem 2.
- Status
- Proposed · as of July 29, 2026
- Location
- Salem Township, west of the Susquehanna nuclear plant · Luzerne County
- Status note
- State permit applications are pending at DEP; land is inside the township's data center overlay, where data centers are allowed by right.
- Power
- Not reported
No power figure published in the sources reviewed. - Land
- 1,700 acres
- Investment
- More than $500 million paid for land from about 96 owners (reported)
- Developer and team
- QTS Data Centers (through Salem Township Holdings LLC)
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Oct. 20, 2026 The state Department of Environmental Protection's data center permit tracker lists 15 environmental permit or authorization entries for the project: 5 pending, 10 not yet submitted. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026; Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
- Aug. 22, 2026 Developers told a public meeting the QTS campus would have about 12 buildings built in phases, with construction to start in late 2026. (Times Leader, Aug. 22, 2026)
- March 19, 2026 QTS completed its purchase of about 1,700 acres, from close to 100 sellers, for more than $500 million. (Data Center Dynamics, March 19, 2026)
- Dec. 8, 2025 Earliest environmental permit application listed for the project on DEP's data center permit tracker submitted. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026; Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
Have records about this project? Send them to tips@signaldata.org.