Data center project · Westmoreland County, Pennsylvania
TECfusions Keystone Connect
Proposed · TECfusions bought part of the former Alcoa research campus to build a data center campus it says could reach 3 GW; one existing building runs while the township writes rules.
- Status
- Proposed · as of Sept. 8, 2026
- Location
- Former Alcoa/Arconic technical center, Upper Burrell Township · Westmoreland County
- Status note
- One existing building (Building J) is operating for a tenant; no work has started on the larger campus. DEP lists its review complete. Neighbors have appealed the township's handling in county court.
- Power
- 3,000 MW
3 GW at full build-out and about 336 MW in a first phase (company figures, 2025); 12 MW was available immediately. - Floor area
- 500,000 sq ft
- Land
- 1,350 acres
- Developer and team
- TECfusions
- Utility
- On-site natural gas generation planned (company)
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Oct. 20, 2026 The state Department of Environmental Protection's data center permit tracker lists 5 environmental permit or authorization entries for the project: 4 issued, 1 pending. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026; Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
- Sept. 8, 2026 Protect PT and two residents had filed a land use appeal in Westmoreland County court, arguing the project needed a zoning hearing board special exception. (Pennsylvania Capital-Star (from PublicSource), Sept. 8, 2026)
- Aug. 5, 2026 The township approved a land development plan for electrical and mechanical upgrades at the existing Building J. (Pennsylvania Capital-Star (from PublicSource), Sept. 8, 2026)
- May 6, 2026 Upper Burrell supervisors voted 3-0 (Resolution 6-2026) to prepare a curative amendment, pausing new data center applications for 180 days. (Upper Burrell Township Board of Supervisors, May 6, 2026)
- Jan. 31, 2025 Earliest environmental permit application listed for the project on DEP's data center permit tracker submitted. (Pennsylvania Department of Environmental Protection, Oct. 20, 2026; Pennsylvania Department of Environmental Protection, Oct. 20, 2026)
- Dec. 2, 2024 TECfusions closed on the former Arconic technical center property, about 1,350 acres. (Data Center Dynamics, Jan. 9, 2025)
Have records about this project? Send them to tips@signaldata.org.