Data center campus · 6368 W Beagley Rd, West Valley City, Salt Lake County, Utah

Aligned SLC-04

Operating as of April 2026

Aligned build-to-scale data center at 6368 W Beagley Rd in West Valley City, on a site separate from Aligned's West Jordan campus. Also known as: Aligned SLC-04.

Cite← Utah data centers
Beaver CountyBox Elder CountyCache CountyCarbon CountyDaggett CountyDavis CountyDuchesne CountyEmery CountyGarfield CountyGrand CountyIron CountyJuab CountyKane CountyMillard CountyMorgan CountyPiute CountyRich CountySalt Lake CountySan Juan CountySanpete CountySevier CountySummit CountyTooele CountyUintah CountyUtah CountyWasatch CountyWashington CountyWayne CountyWeber CountyAligned SLC-04 · Operating
PowerNot statedNot reported in the records found

Who is behind it

ProjectAligned SLC-04Also: Aligned SLC-04
Developer and teamAligned Data Centers
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. The Gardner Institute data summary listed Aligned SLC-04 in West Valley City among operating data centers, at 270 MW. (Kem C. Gardner Policy Institute, University of Utah, April 2026)

  2. Aligned's location page lists SLC-04 at 6368 W Beagley Rd, West Valley City. (Aligned Data Centers, Jan. 2026)

  3. Aligned announced that the first phase of SLC-04, a build-to-scale waterless data center in West Valley, was complete; it called SLC-04 a multi-megawatt facility within roughly 270 MW of company-wide development planned for 2022. (Utah Business (Aligned press release), Feb. 23, 2022)

Conflicts and open questions

  • The address comes from Aligned's Salt Lake City location page.
  • Coordinates set on Beagley Rd near 6400 West using OpenStreetMap; the Census geocoder could not match the street number but confirms that point lies in West Valley City, Salt Lake County.

The full record

Status note
Aligned announced first-phase completion in Feb. 2022, and the 2026 legislative data summary lists the building as operational.
Power note
The Gardner Institute's 2026 data summary lists 270 MW. Aligned's Feb. 2022 release used 270 MW for its company-wide 2022 pipeline and called SLC-04 only a 'multi-megawatt' build-to-suit facility, so the 270 MW figure is not confirmed for this site.
Evidence
Primary public records
Size class
Under 50 MW (outside main scope; kept for completeness)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.