Data center campus · East Bay neighborhood, Provo (around 1507 South / 180 East), Utah County, Utah
B+F Timpanogos Tech Center data center
Denied
as of March 10, 2026
Provo's council unanimously denied a rezoning for a 66,000 sq ft, 6-10 MW data center in East Bay. Council members said the city should first finish its economic master plan. Also known as: Provo East Bay data center.
Power10MW reported · stated
Floor area66,000sq ft
Who is behind it
ProjectB+F Timpanogos Tech Center data centerAlso: Provo East Bay data center
Developer and teamB+F Timpanogos Tech Center LLC
End userNot found in the recordsNot yet named in any record or credited report we have found.
The record, newest first
The Deseret News included the Provo proposal in a list of Utah data center projects that have met local setbacks. (Deseret News, Oct. 10, 2026)
The Provo City Council voted 7-0 to deny the rezoning, which the Planning Commission had recommended. Mayor Marsha Judkins called approval premature while the city works on its economic development plan, and council members questioned the cooling, power-rate and location claims. (Daily Herald, March 11, 2026)
Conflicts and open questions
- This is below the 50 MW threshold and is kept only as a contested denial. Drop it if the cutoff is applied strictly.
- Coordinates are approximate, for the East Bay area near the reported address.
The full record
- Status note
- The Provo City Council voted 7-0 to deny the rezoning, after the Planning Commission had recommended approval.
- Power note
- 6-10 MW, which the applicant's representative said Provo City Power had already allocated to the property (Daily Herald).
- Evidence
- News reports; primary records not yet obtained
- Size class
- Under 50 MW (outside main scope; kept for completeness)