Data center campus · Dugway Proving Ground (Army land), Tooele County, Utah
CyrusOne Dugway Proving Ground data center
Proposed
as of March 26, 2026
The Army conditionally picked CyrusOne to negotiate an enhanced-use lease of about 1,201 acres at Dugway Proving Ground for a hyperscale data center, with initial operations targeted for fiscal 2029. Also known as: Army EUL Dugway data center.
PowerNot statedNot reported in the records found
Site1,201acres
Who is behind it
ProjectCyrusOne Dugway Proving Ground data centerAlso: Army EUL Dugway data center
Developer and teamCyrusOne
End userNot disclosed
The record, newest first
The Army announced a conditional selection of CyrusOne, a company held by funds managed by KKR and BlackRock, for about 1,201 acres at Dugway under an enhanced-use lease (10 U.S.C. 2667), with initial operating capability projected for FY2029. The Corps of Engineers will run negotiations and environmental review; developers are to build their own behind-the-meter power and water. (U.S. Army, March 26, 2026; DefenseScoop, March 26, 2026)
Conflicts and open questions
- Coordinates are a rough placement within Dugway Proving Ground (Tooele County). The specific parcel has not been disclosed.
- No MW, investment or lease term has been published for Dugway. DefenseScoop says a February solicitation pointed to 50-year leases generally.
The full record
- Status note
- The Army conditionally selected CyrusOne for exclusive enhanced-use-lease negotiations. The deal is not final.
- Evidence
- Primary public records
- Size class
- 50 MW or more (tracker scope)