Data center campus · Eagle Mountain, in the Regional Technology Innovation (RTI) overlay west of Utah Lake, Utah County, Utah

Tract Eagle Mountain data center park

Site zoned or marketed as of Jan. 24, 2024

Tract bought more than 668 acres in Eagle Mountain's data-center overlay for a master-planned campus and plans power of 400+ MW from Rocky Mountain Power by 2028.

Cite← Utah data centers
Beaver CountyBox Elder CountyCache CountyCarbon CountyDaggett CountyDavis CountyDuchesne CountyEmery CountyGarfield CountyGrand CountyIron CountyJuab CountyKane CountyMillard CountyMorgan CountyPiute CountyRich CountySalt Lake CountySan Juan CountySanpete CountySevier CountySummit CountyTooele CountyUintah CountyUtah CountyWasatch CountyWashington CountyWayne CountyWeber CountyTract Eagle Mountain data center park · Site zoned or marketed · 400 MW
Power400MW reported · stated
Site668acres

Who is behind it

ProjectTract Eagle Mountain data center park
Developer and teamTract
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. KSL reported the purchase and placed the land west of Utah Lake within the overlay zone. (KSL.com, Jan. 24, 2024)

  2. Utah Business ran Tract's release, which says Tract is working with Rocky Mountain Power to deliver more than 400 MW over new transmission by 2028. (Utah Business (Tract press release), Jan. 19, 2024)

  3. Eagle Mountain posted Tract's release announcing it had bought more than 668 acres in the RTI overlay, where data centers are allowed by right with expedited site-plan review; it says Tract is in Rocky Mountain Power's queue for more than 400 MW. (Eagle Mountain City (posted Tract release), Jan. 17, 2024)

Conflicts and open questions

  • The name 'Pole Canyon' from the lead appears only on commercial trackers and was not confirmed in any opened source, so it is not used.
  • Coordinates come from the lead pointer and are approximate. Opened sources give no parcel or road location.
  • The city's PDF of the release has a placeholder in place of the day; the date shown is from its filename (1.17.2024).
  • iso_rto Non-ISO and balancing_authority PACE apply, since Tract names Rocky Mountain Power.

The full record

Status note
Land bought and zoned by right for data centers through the RTI overlay. No end-user project or site plan was found.
Power note
Tract says it is working with Rocky Mountain Power to deliver more than 400 MW through new transmission by 2028.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.