Volition Spanish Fork data center
Provo-based Volition proposes converting a 1-million-sq-ft Spanish Fork warehouse into a 250 MW off-grid data center powered by gas fuel cells, and the city amended its code 3-2 to allow it. Also known as: Volition.
Who is behind it
The record, newest first
At a special meeting, the council approved the code amendment 3-2, requiring independent verification of noise, vibration and heat and ongoing monitoring. (The Salt Lake Tribune, Sept. 24, 2026)
The council delayed the Title 15 vote again, and Volition said it was weighing whether to move on. (FOX 13 News Utah, Sept. 2, 2026)
After nearly two hours of public comment, the council tabled the code change to Sept. 1. (The Salt Lake Tribune, Aug. 21, 2026)
Volition presented its Title 15 on-site generation proposal to the Spanish Fork City Council: 250 MW of IT load in an existing ~1 million sq ft warehouse, with a draft (not final) DAQ approval order for its fuel cells. (Volition (presentation posted on Utah Public Notice Website for Spanish Fork City Council), Aug. 18, 2026; Volition (posted on Utah Public Notice Website), Aug. 2026)
Conflicts and open questions
- Site confirmed by the Tribune (Aug. 21 and Sept. 24): 4000 E. U.S. 6, the former Fingerhut warehouse at the mouth of Spanish Fork Canyon. The lead's address (1604 W 4350 N) appears in no opened source and is not this site.
- Coordinates are approximate, at the mouth of Spanish Fork Canyon near the reported address.
- The Volition documents are developer-prepared and were posted on the Utah Public Notice site.
The full record
- Status note
- The city council approved a code amendment 3-2 on Sept. 21, 2026 allowing self-powered data centers, with conditions. A site plan, Utah DAQ air permits and a development agreement are still needed.
- Power note
- 250 MW of IT load (Volition). Volition's deck cites a draft DAQ notice for 1,210 fuel-cell units at about 393 MW nameplate; the Tribune says about 400 MW would be needed. The proposed city amendment (Aug.) would cap power at 500 MW.
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)