Data center campus · Hansel Valley, unincorporated Box Elder County, Box Elder County, Utah

Wonder Valley Utah (Stratos Project)

Approved as of May 4, 2026

A proposed hyperscale data center and on-site gas power campus from Kevin O'Leary's O'Leary Digital inside a roughly 40,000-acre MIDA project area in Hansel Valley, Box Elder County. Also known as: Stratos Project, Stratos Project Area, Wonder Valley.

Cite← Utah data centers
Beaver CountyBox Elder CountyCache CountyCarbon CountyDaggett CountyDavis CountyDuchesne CountyEmery CountyGarfield CountyGrand CountyIron CountyJuab CountyKane CountyMillard CountyMorgan CountyPiute CountyRich CountySalt Lake CountySan Juan CountySanpete CountySevier CountySummit CountyTooele CountyUintah CountyUtah CountyWasatch CountyWashington CountyWayne CountyWeber CountyWonder Valley Utah (Stratos Project) · Approved · 1,100 MW
Power1,100MW reported · stated
Site40,692acres

Who is behind it

ProjectWonder Valley Utah (Stratos Project)Also: Stratos Project, Stratos Project Area, Wonder Valley
Developer and teamO'Leary Digital (through O'Leary Digital Utah Development Company, LLC (MIDA master developer))
End userNot found in the recordsNot yet named in any record or credited report we have found.

The record, newest first

  1. An O'Leary Digital affiliate filed a new water-rights change application with the Division of Water Rights describing 11 data center clusters and 7.5 GW of generation; close to 200 protests were logged within days. (KSL.com (republished by Deseret News), Oct. 16, 2026; The Salt Lake Tribune, Oct. 20, 2026)

  2. The company said the project was in pre-development, with Phase 1 generation limited to 1.5 GW; three related lawsuits remained unresolved. (KSL.com (republished by Deseret News), Oct. 2, 2026)

  3. The county and O'Leary's side asked the 1st District Court to dismiss the referendum lawsuit. (FOX 13 News, Aug. 3, 2026)

  4. MIDA said its work was paused with no action before it and while the referendum appeal proceeds; O'Leary said design work continued and about 10,000 acres would be developed. (The Salt Lake Tribune, July 29, 2026)

  5. The county adopted Ordinance 654, a 180-day pause on new data center applications that does not apply to the Stratos area, where MIDA holds land-use authority. (Box Elder County, June 10, 2026)

  6. Gov. Spencer Cox signed an executive order setting a statewide data center framework; earlier in May he had said five state agencies must approve parts of the Stratos project before Phase 1 construction. (Deseret News, May 29, 2026)

  7. The county attorney rejected three referendum applications aimed at the two May 4 resolutions, finding them administrative acts that cannot be referred to voters. (Utah News Dispatch, May 28, 2026)

  8. O'Leary Digital released early renderings: a cluster of ten 100 MW data center buildings plus another 100 MW building, about 1 GW of gas generation with batteries, and a 3,000-acre, 500 MW solar array; the project area is split into three sites and permits could take years. (Utah News Dispatch (republished by KPCW), May 20, 2026)

  9. On 3-0 roll-call votes, commissioners adopted Resolution 26-12 approving the interlocal agreement and Resolution 26-11 consenting to the inclusion of private land in the Stratos project area; minutes estimate about 1,000 people attended. (Box Elder County Commission, May 4, 2026; Utah News Dispatch (republished by Idaho Capital Sun), May 4, 2026; The Logic, May 5, 2026)

  10. KUTV reported resident concerns about water, noise, emissions and wildlife; MIDA projected about 2,000 permanent jobs. (KUTV, April 30, 2026)

  11. At a special meeting, Box Elder County commissioners tabled the interlocal agreement (#26-15) and the consent resolution, citing new information, and moved the decision to a May 4 meeting at the county fairgrounds. (Box Elder County Board of County Commissioners, April 27, 2026; Box Elder County Commission, April 27, 2026; Utah News Dispatch (republished by Idaho Capital Sun), May 4, 2026)

  12. MIDA's board packet included the Stratos Project Area Plan (about 40,692 private acres plus about 1,279 acres of military and state land), development standards, a master development agreement with O'Leary Digital Utah Development Company, an energy sales and use tax ordinance and an interlocal agreement with Box Elder County. (Military Installation Development Authority (Utah Public Notice Website), April 24, 2026)

Conflicts and open questions

  • Coordinates are from the internal lead pointer; they fall within T12N R7W SLM, inside the township range listed in MIDA plan Exhibit A (T12N-T13N, R7W-R10W), in Box Elder County. Parcels were not individually mapped.
  • Acreage: MIDA plan Exhibit A gives 40,691.72 private acres plus 1,278.96 acres of military/state land; O'Leary told the Tribune in July 2026 that about 10,000 acres would be built on, and in October the Tribune reported about 11,000 acres under purchase agreements.
  • Resolution numbers confirmed from the county's May 4, 2026, agenda and approved minutes: Resolution 26-11 (consent to the project area) and Resolution 26-12 (approving Interlocal Agreement 26-15). The April 27 agenda had listed the consent item as Resolution 26-10, while the special-meeting order attached to the April 27 minutes called it 26-11.
  • Power figures vary: 7.5 GW (The Logic; Oct. 2026 water filing), 7.5 to 9 GW (county release via Utah News Dispatch), up to 9 GW long term with 1.5 GW in Phase 1 (KSL, Oct. 2026).
  • The draft MIDA-county interlocal agreement in MIDA's April 24 packet estimates county revenue of about $30 million a year from a roughly 3 GW first phase and about $108 million a year at about 9 GW, with MIDA agreeing to adjust its tax to guarantee those minimums. These are draft-agreement estimates, not the adopted text.

The full record

Status note
On May 4, 2026, Box Elder County consented to the MIDA Stratos project area (Resolution 26-11) and approved the interlocal agreement (Resolution 26-12); the company says it is in pre-development, filed a new water-rights change application in October 2026, and still needs state approvals before Phase 1.
Power note
About 1,100 MW of data center buildings, taken from the company's May 2026 renderings (ten 100 MW buildings plus one more 100 MW building); unconfirmed by any filing. Generating capacity is reported separately and is larger: KSL (Oct. 2026) reports Phase 1 generation limited to 1.5 GW and up to 9 GW long term; The Logic and the October 2026 water filing describe 7.5 GW.
Evidence
Primary public records
Size class
50 MW or more (tracker scope)
Map position approximate, from the reported address or area. Updated Oct. 17, 2026.