Data center project · Klickitat County, Washington
Energizer Data Center (BPA queue L0493)
Inquiry only · A 78 MW data center connection request in BPA's queue for ranch land in the Columbia Hills; BPA's facility study is done.
- Status
- Inquiry only · as of Sept. 2, 2026
- Location
- Hoctor Road, Columbia Hills area · Klickitat County
- Status note
- A utility interconnection request in BPA's queue only; a queue listing is not an approval.
- Power
- 78 MW
Maximum summer and winter load requested in BPA's queue, as reported; not an approved load. - Developer and team
- Not named (landowner 101 Bar Ranches LLC)
- Utility
- Klickitat County PUD (Energizer Substation, through BPA's transmission queue)
- Evidence
- News reports; primary records not yet obtained
- Size class
- 50 MW or more (tracker scope)
Updates, newest first
- Sept. 2, 2026 The Goldendale Sentinel reported BPA's queue lists the project as in progress with its facility study completed. (Goldendale Sentinel, Sept. 2, 2026)
- June 29, 2021 The large-load request was submitted, according to BPA's queue as reported by the Goldendale Sentinel. (Goldendale Sentinel, Sept. 2, 2026)
Conflicts and open questions
- The request was submitted in 2021, before this tracker's 2024 window; it is listed because it was first reported in 2026 and is still in progress.